1 |
MAT/PUR/10693/18 |
Supply of SULPHURIC ACID, as per IS-266(1993),Purity (%w/w) minimum: 98% |
07-09-2018 |
19-09-2018 |
|
2 |
2207/MEC30138 DTD.07.09.2018 |
MAINTENANCE OF HEAT EXCHANGERS - FRACTIONATION |
14-09-2018 |
28-09-2018 |
|
3 |
2211/MEC30139 DTD.07.09.2018 |
MAINTENANCE OF FAC OVERHEAD CONDENSER - (E 4507 A&B) & EVAPORATOR PRE-FLASH CONDENSER (E 3002) |
14-09-2018 |
28-09-2018 |
|
4 |
MEC30136/2171 |
PREPARATORY WORKS FOR STATUTORY INSPECTION OF SPHERES AND PROPYLENE BULLETS UNDER SMPV(U) RULES - 1981 |
25-10-2018 |
24-10-2018 |
|
5 |
MAT/PUR/32443/18 |
SS PIPE; RFQ NO.6000019394/2243/32443 |
27-10-2018 |
26-10-2018 |
|
6 |
MAT/PUR/32432/18 |
Supply of 2 Micron Heat Purified fibre glass
filter with extended SS core
|
31-10-2018 |
30-10-2018 |
|
7 |
MAT/PUR/10696/18 |
TRANSPORTATION OF LSFO/ FURNACE OIL
FROM BPCL, IRIMBANAM / WILLINGDON
ISLAND TO HOCL, AMBALAMUGAL, FOR A
PERIOD OF ONE YEAR
|
24-10-2018 |
23-10-2018 |
|
8 |
MAT/PUR/80001-M/18 |
Supply of CS GATE, GLOBE & CHECK Valves as per attached RFQ No6000019619 |
01-11-2018 |
31-10-2018 |
|
9 |
MAT/PUR/80002-M/18 |
Supply of SS GATE, GLOBE & CHECK Valves-80002 |
01-11-2018 |
31-10-2018 |
|
10 |
2018_HOCL_397584_1 |
Supply of Aluminium sheets (as per attached RFQ No.6000019639/2265/800003-M) |
01-11-2018 |
31-10-2018 |
|
11 |
CIV10063/2018 |
MISCELLANEOUS CIVIL MAINTENANCE WORK IN PLANT AND NON PLANT AREAS 2018-19 |
03-11-2018 |
02-11-2018 |
|
12 |
MAT/PUR/80004-M/18 |
SUPPLY OF CS SEAMLESS PIPE |
06-11-2018 |
05-11-2018 |
|
13 |
MAT/PUR/80008-M/18 |
SUPPLY OF CS SEAMLESS TUBE IBR |
06-11-2018 |
05-11-2018 |
|
14 |
MAT/PUR/80009-M/18 |
SUPPLY OF SS SEAMLESS PIPE |
06-11-2018 |
05-11-2018 |
|
15 |
2266/80007-M |
CAF GASKET |
02-11-2018 |
02-11-2018 |
|
16 |
MAT/PUR/80006-M/18 |
CAF GASKETS-80006-M |
01-11-2018 |
31-10-2018 |
|
17 |
MAT/PUR/50331/18 |
SUPPLY OF 2 METHYL CYCLO HEXYL ACETATE |
13-11-2018 |
12-11-2018 |
|
18 |
PAD/2018/00006 |
HOUSEKEEPING AND WASTE DISPOSAL AT TOWNSHIP FOR THE YEAR 2018-2019 (LIMITED TENDER) |
30-10-2018 |
29-10-2018 |
|
19 |
MAT/PUR/80011-M/18 |
SUPPLY OF SS TUBE |
09-11-2018 |
08-11-2018 |
|
20 |
MAT/PUR/80012-M/18 |
SUPPLY OF SS 316 U TUBE |
09-11-2018 |
08-11-2018 |
|
21 |
MAT/PUR/80016-M/18 |
SUPPLY OF RODS AND PLATES |
14-11-2018 |
13-11-2018 |
|
22 |
MAT/PUR/80013-M/18 |
SUPPLY OF CS TUBE |
13-11-2018 |
12-11-2018 |
|
23 |
MAT/PUR/80015-M/18 |
SUPPLY OF CS SEAMLESS PIPE |
13-11-2018 |
12-11-2018 |
|
24 |
MAT/PUR/41619 |
UL LISTED MAP DRY CHEMICAL POWDER |
15-11-2018 |
14-11-2018 |
|
25 |
MAT/PUR/50330/18 |
SUPPLY OF 2 ETHYLANTHRAQUINON |
20-11-2018 |
19-11-2018 |
|
26 |
MAT/PUR/80017-M |
PIPE FITTINGS |
15-11-2018 |
14-11-2018 |
|
27 |
MKT/DRUM/MISC/10/18/3 |
FILLING AND LOADING OF PHENOL,ACETONE AND HYDROGEN PEROXIDE IN DRUMS/CARBOUYS |
20-11-2018 |
19-11-2018 |
|
28 |
MAT/PUR/80018-M/18 |
CS STUD WITH NUT |
20-11-2018 |
19-11-2018 |
|
29 |
MAT/PUR/80019-M/18 |
CS VALVES IBR |
22-11-2018 |
21-11-2018 |
|
30 |
MAT/PUR/80021-M/18 |
SS SEAMLESS COLD BEND U TUBE |
22-11-2018 |
21-11-2018 |
|
31 |
PAD/2018/00007 |
GRASS CUTTING |
06-12-2018 |
05-12-2018 |
|
32 |
HOC/MSS/608/2018-19 |
Tally ERP 9.0 server implementation |
29-12-2018 |
28-12-2018 |
|
33 |
ELE/H2O2-UTY/527 |
AMC OF MISCELLANEOUS WORKS 2018-2019 |
05-12-2018 |
05-12-2018 |
|
34 |
MAT/PUR/80022-M/18 |
Supply of Flanges & caps |
28-11-2018 |
27-11-2018 |
|
35 |
MAT/PUR/80024-M/18 |
Supply of Butterfly Valves |
28-11-2018 |
27-11-2018 |
|
36 |
MAT/PUR/80004-M/18 |
Supply of CS Seamless pipes |
29-11-2018 |
28-11-2018 |
|
37 |
MAT/PUR/80009-M/18 |
SS Seamless pipe |
29-11-2018 |
28-11-2018 |
|
38 |
MAT/PUR/80023-M/18 |
Supply of CS Seamless pipe |
01-12-2018 |
30-11-2018 |
|
39 |
MEC30146/2304 |
Maintenance of Vessels in Cumene & Propylene plant |
06-12-2018 |
05-12-2018 |
|
40 |
MEC30150/2307 |
Maintenance of Columns in Cumox ,DNET& Fractionation |
06-12-2018 |
05-12-2018 |
|
41 |
MEC30143/2302 |
maintenance of Vessels in Cumox & DNET |
06-12-2018 |
05-12-2018 |
|
42 |
MEC30151/2303 |
Maintenance of Vessels in Fractionation and Hydrogenation |
06-12-2018 |
05-12-2018 |
|
43 |
MEC30147/2305 |
Maintenance of Vessels in Utilities |
06-12-2018 |
05-12-2018 |
|
44 |
MEC30145/2306 |
Maintenance of Columns in Cumene & Propylene plant |
06-12-2018 |
05-12-2018 |
|
45 |
2340 |
Relay Testing 2019 |
14-12-2018 |
14-12-2018 |
|
46 |
MAT/PUR/10699/18 |
Supply of Sulphuric Acid |
06-12-2018 |
05-12-2018 |
|
47 |
MAT/PUR/21802/18 |
Supply of Tubular battery |
30-11-2018 |
29-11-2018 |
|
48 |
2340 |
RELAY TESTING 2019 |
14-12-2018 |
14-12-2018 |
|
49 |
MAT/PUR/32410/18 |
MECHANICAL SEAL AND SPARES |
13-12-2018 |
12-12-2018 |
|
50 |
HOC/MSS/608/2018-19 |
TALLY ERP 9.0 SERVER IMPLEMENTATION |
29-12-2018 |
28-12-2018 |
|
51 |
MAT/PUR/80006-M/18 |
CAF GASKET |
11-12-2018 |
10-12-2018 |
|
52 |
MEC30148/2323 |
CLEANING OF HEAT EXCHANGER TUBE BUNDLES BY HYDROBLASTING METHOD |
13-12-2018 |
12-12-2018 |
|
53 |
MEC30153/2333 |
CRITICAL INSPECTION OF PIPING AND EQUIPMENTS IN PHENOL PLANT |
20-12-2018 |
19-12-2018 |
|
54 |
MEC30149/2331 |
INSULATION,WRAPPING AND COATING WORKS |
20-12-2018 |
19-12-2018 |
|
55 |
MAT/PUR/80030/18 |
SUPPLY OF CS ERW PIPES |
15-12-2018 |
14-12-2018 |
|
56 |
MEC30128/2343 |
ULTRASONIC THICKNESS SURVEY OF PIPING AND EQUIPMENTS |
20-12-2018 |
19-12-2018 |
|
57 |
MEC30166/2355 |
REPAIRS AND RECONDITIONING OF HS ROTOR OF CENTRIFUGAL PROCESS AIR COMPRESSOR-K 2501 A |
03-01-2019 |
02-01-2019 |
|
58 |
MAT/PUR/80026-E/18 |
COPPER CABLE |
20-12-2018 |
19-12-2018 |
|
59 |
MAT/PUR/80027-E/18 |
FLP LED LIGHT-FITTINGS |
12-12-2018 |
11-12-2018 |
|
60 |
MAT/PUR/21807/18 |
UPS SYSTEM WITH SCVS |
21-12-2018 |
20-12-2018 |
|
61 |
MAT/PUR/80036-M/18 |
TEFLON/VITON RUBBER SHEETS |
27-12-2018 |
26-12-2018 |
|
62 |
CIV10066/2018 |
REPLACING THE ENTIRE CEMENT ROOFING |
27-12-2018 |
26-12-2018 |
|
63 |
MAT/PUR/50330-B/18 |
2 ETHYLANTHRAQUINON |
27-12-2018 |
26-12-2018 |
|
64 |
HOC/MSS/608/2018-19 |
TALLY ERP 9.0 SERVER IMPLEMENTATION_CORRIGENDUM_1 |
29-12-2018 |
28-12-2018 |
|
65 |
HOC/MSS/608/2018-19 |
TALLY ERP 9.0_CORRIGENDUM2 |
29-12-2018 |
28-12-2018 |
|
66 |
Corp/Admn./HV/2018 |
Tender for providing one tourist car on monthly hire basis for senior executive of the Company. |
26-12-2018 |
26-12-2018 |
|
67 |
MAT/PUR/80038-M/18 |
TAR COLUMN AND AMS COLUMN TRAY ASSEMBLY |
28-12-2018 |
27-12-2018 |
|
68 |
MAT/PUR/21810/18 |
TRANSFORMER OIL |
05-01-2019 |
04-01-2019 |
|
69 |
Corp/Admn./HV/2018. |
Tender for providing one tourist car for senior
executive of the Company. |
26-12-2018 |
26-12-2018 |
|
70 |
CIV10068/2018 |
ASSESSMENT OF STRUCTURAL SOUNDNESS |
27-12-2018 |
26-12-2018 |
|
71 |
MEC30152/2377 |
CUMENECATALYST UNLOADING AND LOADING |
21-12-2018 |
20-12-2018 |
|
72 |
MEC30167/2370 |
REMOVAL AND REFIXING OF SOOT BLOWERS MAIN BOILERS |
29-12-2018 |
28-12-2018 |
|
73 |
HOC/MSS/608/2018-2019 |
TALLY ERP 9.0 SERVER |
29-12-2018 |
28-12-2018 |
|
74 |
MAT/PUR/10701/18 |
CAUSTIC SODA LYE |
10-01-2019 |
09-01-2019 |
|
75 |
CIV10070 |
MISCELLANEOUS CIVIL MAINTENANCE WORK IN TOWNSHIP 2018-19 |
08-01-2019 |
07-01-2019 |
|
76 |
MAT/PUR/80024M B/18 |
BUTTERFLY VALVE |
04-01-2019 |
03-01-2019 |
|
77 |
MAT/PUR/80024M B/18 |
BUTTERFLY VALVE |
04-02-2019 |
03-01-2019 |
|
78 |
2389 |
BOCB OVERHAULING |
16-01-2019 |
16-01-2019 |
|
79 |
MAT/PUR/80044-M/18 |
TUBE FOR HEAT EXCHANGERS |
28-12-2018 |
27-12-2018 |
|
80 |
Corp/Admn./HV/2018 |
Tender for tourist car on monthly hire basis for senior
executive of the Company.
|
03-01-2019 |
03-01-2019 |
|
81 |
MEC30154 |
PIPING WORK NON IBR |
10-01-2019 |
09-01-2019 |
|
82 |
MEC30162 |
FABRICATION AND ASSEMBLING OF E-2501 & E-5003 |
10-01-2019 |
09-01-2019 |
|
83 |
HOC/MSS/608/2018-2019 |
EXTENSION OF DUE DATE FOR ONLINE BID SUBMISSION- TALLY ERP 9.0 SERVER IMPLEMENTATION |
05-01-2019 |
04-01-2019 |
|
84 |
MAT/PUR/80051M B/18 |
EDUCTORS |
15-01-2019 |
14-01-2019 |
|
85 |
MAT/PUR/80045M B/18 |
SS PLATES |
11-01-2019 |
10-01-2019 |
|
86 |
MAT/PUR/80054M B/18 |
SS FLANGED VALVES |
11-01-2019 |
10-01-2019 |
|
87 |
MEC30171/2403 |
VALVES REPAIRING, OVERHAULING AND SERVICING |
19-01-2019 |
18-01-2019 |
|
88 |
MEC30163/2397 |
REPAIRING OF STRUCTRUAL PLATFORM |
22-01-2019 |
21-01-2019 |
|
89 |
MAT/PUR/21816 |
MOTOR OPERATING MECHANISM |
31-01-2019 |
30-01-2019 |
|
90 |
MAT/PUR/80038-M/18 |
TRAY ASSEMBLY |
29-01-2019 |
28-01-2019 |
|
91 |
MAT/PUR/70642/18 |
FIRE SAFE ROV (3) |
31-01-2019 |
30-01-2019 |
|
92 |
MEC30170/2400 |
MISCELLANEOUS WORKS OF SCAFFOLDING ERECTION AND DISMANTLING |
23-01-2019 |
23-01-2019 |
|
93 |
MEC30164/2429 |
INTER CONNECTION OF C3C4 AND C3C3 CONDENSER |
06-02-2019 |
05-02-2019 |
|
94 |
MEC30162/2407 |
REPAIR OF SPRINKLER SYSTEM IN SPHERE AREA |
01-02-2019 |
31-01-2019 |
|
95 |
CIV10066/2018 |
REPLACING THE ENTIRE ASBESTORS CEMENT ROOFING SHEETS OF BOILER HOUSE ROOF |
02-02-2019 |
01-02-2019 |
|
96 |
CIV10067/2018 |
PROVIDING/REPLACING BARBED WIRE FENCING AT EXPLOSIVE LICENCED AREA |
06-02-2019 |
05-02-2019 |
|
97 |
MAT/PUR/21810/18 |
TRANSFORMER OIL |
06-02-2019 |
05-02-2019 |
|
98 |
MAT/PUR/80051M B/18 |
EDUCTORS |
07-02-2019 |
06-02-2019 |
|
99 |
MAT/PUR/80036M B/18 |
TEFLON/VITON RUBBER SHEET |
05-02-2019 |
04-02-2019 |
|
100 |
MAT/PUR/80065M B/18 |
CS PIPES |
06-02-2019 |
05-02-2019 |
|
101 |
CIV10072/2018 |
REMOVAL OF BLACK COLOURED SOIL FROM THE SOUTH EAST SIDE OF COMPOUND WALL |
06-02-2019 |
06-02-2019 |
|
102 |
ELE/H2O2-UTY/530 |
AMC FOR WINDOW AC, SPLIT AC AND WATER COOLERS 2019-20 |
20-02-2019 |
20-02-2019 |
|
103 |
ELE/PLANT/412 |
AMC OF 40 ZONE FIRE ALARM SYSTEM 2019-20 |
20-02-2019 |
20-02-2019 |
|
104 |
MAT/PUR/21807B/18 |
2*20 KVA UPS SYSTEM WITH SCVS FOR PHENOL PLANT |
15-02-2019 |
14-02-2019 |
|
105 |
CIV10073/2018 |
REPAIRS TO RCC STRUCTURES IN PLANT AREAS |
23-02-2019 |
22-02-2019 |
|
106 |
MEC30172/2441 |
RE TUBING OF OVERHEAD CONDENSER |
14-02-2019 |
13-02-2019 |
|
107 |
MEC30172/2441 |
RETUBING OF OVERHEAD CONDENSER |
14-02-2019 |
13-02-2019 |
|
108 |
MEC30134 |
REFRACTORY REPAIR WORK IN HOT OIL HEATER |
15-02-2019 |
15-02-2019 |
|
109 |
MEC30169/2445 |
IN SITU METALLOGRAPHY OF HOT OIL HEATER |
20-02-2019 |
20-02-2019 |
|
110 |
MEC30176/2469 |
PTFE LINED PIPING |
22-02-2019 |
21-02-2019 |
|
111 |
MEC30173/2450 |
PIPING WORK IBR |
22-02-2019 |
21-02-2019 |
|
112 |
MEC30155/2384 |
SUPPLY APPLICATION AND ERECTION OF FRP LINING |
22-02-2019 |
22-02-2019 |
|
113 |
MEC30158/2448 |
STENCILING ARROWS LETTERS AND NUMBERS ON EQUIPMENTS AND PIPELINES |
27-02-2019 |
26-02-2019 |
|
114 |
MEC30168/2446 |
CLEANING OF HOT OIL HEATER TUBES PREPARATION FOR NDT IN SITU METALLOGRAPHY |
20-02-2019 |
19-02-2019 |
|
115 |
MEC30156/2353 |
IN SITU MACHINING OF FLANGES |
28-02-2019 |
27-02-2019 |
|
116 |
MEC30174/2470 |
CLEANING OF COOLING TOWER |
22-02-2019 |
22-02-2019 |
|
117 |
EOI for Power |
Expression of interest for power generation in Phenol plant of HOCL |
01-04-2019 |
31-03-2019 |
|
118 |
MAT/PUR/80041-M/18 |
PROCUREMENT OF PSV |
27-02-2019 |
26-02-2019 |
|
119 |
MAT/PUR/80063-M |
HIGH PRESSURE CLEANER PUMP |
01-03-2019 |
28-02-2019 |
|
120 |
MAT/PUR/21816-B/18 |
MOTOR OPERATING MECHANISM FOR 66 KV ISOLATOR |
28-02-2019 |
27-02-2019 |
|
121 |
MAT/PUR/10705/18 |
HM-HDPE CARBOUYS |
12-03-2019 |
11-02-2019 |
|
122 |
MAT/PUR/10705/18 |
HDPE CARBOUYS |
12-03-2019 |
11-03-2019 |
|
123 |
MAT/PUR/70644/18 |
ON-LINE CONTINUOUS STACK |
12-03-2019 |
11-03-2019 |
|
124 |
MAT/PUR/80055-M/18 |
MS PLATES |
05-03-2019 |
04-03-2019 |
|
125 |
FIN/INS/ENQ/2019-20 |
Renewal of insurance policy |
13-03-2019 |
13-03-2019 |
|
126 |
MAT/PUR/32465/18 |
MECHANICAL SEAL |
16-03-2019 |
15-03-2019 |
|
127 |
MAT/PUR/80075-M/18 |
INSULATION WOOL, FOIL |
12-03-2019 |
11-03-2019 |
|
128 |
MEC30167 |
REMOVAL AND REFIXING OF SOOT BLOWERS FOR MAIN BOILERS- K 479 &K 480 |
07-03-2019 |
06-03-2019 |
|
129 |
MEC30177 |
SUPPLY FABICATION & TESTING |
14-03-2019 |
13-03-2019 |
|
130 |
MAT/PUR/18 |
FIRE SAFE ROV |
15-03-2019 |
14-03-2019 |
|
131 |
MAT/PUR/10700/18 |
BENZENE |
22-03-2019 |
21-03-2019 |
|
132 |
Auction : MSTC/WRO/HOCL Ltd/8/18-19/33299[204105]Type : P |
Auction for the Sale of Panvel Land 8 acres owned by HOCL. Land located near Panvel Goa Highway & Panvel Poona Express Highway.
HOCL के स्वामित्व वाली 8 एकड़ जमीन की बिक्री के लिए नीलामी। पनवेल गोवा राजमार्ग और पनवेल पूना एक्सप्रेस राजमार्ग के पास स्थित भूमि |
24-04-2019 |
24-04-2019 |
|
133 |
MAT/PUR/10706/18 |
SULPHURIC ACID |
22-03-2019 |
21-03-2019 |
|
134 |
MAT/PUR/10707/18 |
HIRING OF STORAGE TANK |
22-03-2019 |
21-03-2019 |
|
135 |
MAT/PUR/41633/18 |
SAFETY ITEMS |
02-04-2019 |
01-04-2019 |
|
136 |
MEC30174/2470 |
CLEANING OF COOLING TOWER |
19-03-2019 |
18-03-2019 |
|
137 |
MEC30174/18 |
CLEANING OF COOLING TOWER |
19-03-2019 |
18-03-2019 |
|
138 |
MEC30174/2470 |
CLEANING OF COOLING TOWER |
19-03-2019 |
18-03-2019 |
|
139 |
MAT/PUR/41644/19 |
SUPPLY , INSTALLATION, CONFIGURATION, TESTING, COMMISSIONING AND MAINTENANCE OF SERVER FOR TALLY ERP 9.0 SERVER IMPLEMENTATION |
12-04-2019 |
11-04-2019 |
|
140 |
CIV10074/18 |
ARRANGEMENTS OF AC CABIN IN MRS |
27-03-2019 |
27-03-2019 |
|
141 |
MAT/PUR/80051-M-C/19 |
EDUCTORS |
09-04-2019 |
08-04-2019 |
|
142 |
MAT/PUR/80038-M-C/19 |
COMPLETE COLOUMN TRAY ASSEMBLY |
09-04-2019 |
08-04-2019 |
|
143 |
MAT/PUR/50334/18-19 |
Supply of 2-Methyl Cyclohexyl Acetate (2 MCA) |
23-04-2019 |
22-04-2019 |
|
144 |
MEC30179/2516 |
EXTENSION OF TENDER PAINTING OF PIPELINE AND STRUTURALS |
26-04-2019 |
25-04-2019 |
|
145 |
MSTC/WRO/HOC/8/18-19/33299(204105) TYPE P |
Corrigendum in respect of E Auction of Panvel land.
पनवेल भूमि के ई नीलामी के संबंध में कोरिगेंडम |
24-04-2019 |
24-04-2019 |
|
146 |
MAT/PUR/80078-M/19 |
BUTTERFLY VALVES |
17-04-2019 |
16-04-2019 |
|
147 |
MAT/PUR/32476/19 |
CLARIFIED WATER PUMP |
23-04-2019 |
22-04-2019 |
|
148 |
PREMONSOON MAINTENANCE WORK IN PLANT AND NON PLANT AREAS |
CIV10076/2019 |
12-04-2019 |
12-04-2019 |
|
149 |
MAT/PUR/32475/19 |
PLATE HEAT EXCHANGER ASSEMBLY |
30-04-2019 |
29-04-2019 |
|
150 |
ELE/H2O2-UTY/525/2544 |
AMC WINDOW AC SPLIT AC AND WATER COOLERS 2019-20 |
03-05-2019 |
03-05-2019 |
|
151 |
MEC30181/2530 |
REPAIR OF PACKAGE BOILER STACK |
24-04-2019 |
23-04-2019 |
|
152 |
MAT/PUR/32480/19 |
SUPPLY STRUCTURAL STEEL |
07-05-2019 |
06-05-2019 |
|
153 |
MEC30182/2532 |
HOT OIL HEATER SHELL PLATE |
02-05-2019 |
30-04-2019 |
|
154 |
HV_REQ/2019 |
Tender for providing A/c vehicles on as and when required basis for official use on Annual Rate Contract basis for a period of two years- for corporate office Mumbai
|
13-05-2019 |
13-05-2019 |
|
155 |
MEC30179/2516 |
EXTENSION OF TENDER PAINTING OF PIPELINE AND STRUTURALS |
26-04-2019 |
25-04-2019 |
|
156 |
ELE/H2O2-UTY/534 |
SHIFTING OF RECTIFIER TRANSFORMER 1 AT HYDRPOGEN 2 PLANT |
15-05-2019 |
15-05-2019 |
|
157 |
MEC30179/2516 |
EXTENSION OF TENDER PAINTING OF PIPELINE |
26-04-2019 |
25-04-2019 |
|
158 |
MAT/PUR/32476B |
CLARIFIED WATER PUMP |
17-05-2019 |
16-05-2019 |
|
159 |
MAT/PUR/10713/19 |
MS BARRELS |
23-05-2019 |
22-05-2019 |
|
160 |
PAD/2019/00001 |
UNSKILLED LABOURS FOR CASUAL JOBS OF MISCELLANEOUS NATURE |
28-05-2019 |
27-05-2019 |
|
161 |
HOC/ELE/PLANT/413 |
AMC OF TELEPHONE LINES IN FACTORY AND TOWNSHIP 2019-2020 |
24-05-2019 |
23-05-2019 |
|
162 |
Corp/Admn./HV/2019 |
Tender for providing one tourist car on monthly hire basis at Corporate office in Mumbai
मुंबई में HOCL के कॉर्पोरेट कार्यालय में मासिक किराए के आधार पर एक पर्यटक कार प्रदान करने के लिए निविदा |
28-05-2019 |
28-05-2019 |
|
163 |
MAT/PUR/80063M-B/19 |
HIGH PRESSURE CLEANER PUMP |
29-05-2019 |
28-05-2019 |
|
164 |
MAT/PUR/50334B/19 |
2 MCA |
05-06-2019 |
04-06-2019 |
|
165 |
MAT/PUR/10718/19 |
SUPPLY OF HYDROGEN-EXTENSION |
22-05-2019 |
21-05-2019 |
|
166 |
MAT/PUR/10717/19 |
TRANSPORTATION OF HYDROGEN PEROXIDE IN BULK IN TANKERS
OF CAPACITY 9 TO 10 MT TO VARIOUS DESTINATIONS DEPENDING
ON ORDERS RECEIVED BY THE COMPANY FOR A PERIOD OF TWO
YEARS FROM 15.6.2019 |
06-06-2019 |
05-06-2019 |
|
167 |
CIV10077/2019 |
HIRING OF MECHANICAL EXCAVATOR, TIPPER AND PUMP SET |
31-05-2019 |
30-05-2019 |
|
168 |
MAT/PUR/70642-B/18 |
FIRE SAFE ROV & BALL VALVE |
06-06-2019 |
05-06-2019 |
|
169 |
UTY30138/2560 |
ANNUAL CLEANING AND INSPECTION OF BOILERS -K 479 & K 480 & K 607 |
10-06-2019 |
07-06-2019 |
|
170 |
MAT/PUR/32489/19 |
JOCKEY PUMP FOR FIRE WATER SYSTEM |
11-06-2019 |
10-06-2019 |
|
171 |
HOC/MSS/515/2019 |
AMC FOR DATA CENTER 2019-2020 |
15-06-2019 |
14-06-2019 |
|
172 |
MAT/PUR/32475-B/19 |
PLATE HEAT EXCHANGER ASSEMBLY |
19-06-2019 |
18-06-2019 |
|
173 |
2548 |
SHIFTING OF RECTIFIER TRANSFORMER- 1 AT HYDROGEN 2 PLANT - REFLOAT |
07-06-2019 |
07-06-2019 |
|
174 |
MAT/PUR/32490/19 |
SPARES FOR DRESSER-RAND COMPRESSORS |
20-06-2019 |
19-06-2019 |
|
175 |
MAT/PUR/32491/19 |
SPARES FOR CPT COMPRESSOR |
20-06-2019 |
19-06-2019 |
|
176 |
MEC30185/2566/19 |
RECONDITIONING OF CPP ENGINE NO 1 |
19-06-2019 |
18-06-2019 |
|
177 |
MAT/PUR/32499/19 |
CS PIPES |
03-07-2019 |
02-07-2019 |
|
178 |
MAT/PUR/70642-C/18 |
FIRE SAFE ROV & BALL VALVE |
29-06-2019 |
28-06-2019 |
|
179 |
MAT/PUR/32504/2019 |
KHOSLA COMPRESSOR SPARES |
05-07-2019 |
04-07-2019 |
|
180 |
HOC/QC/40/2019 |
AMBIENT AIR, STACK EMMISION & EMMISSION MONITORING OF HEAVY MOVING EQUIPMENTS 2019-2020 |
02-07-2019 |
01-07-2019 |
|
181 |
MAT/PUR/10717B/19 |
TRANSPORTATION OF HYDROGEN PEROXIDE IN BULK IN TANKERS OF CAPACITY 9 TO 10 MT |
19-07-2019 |
18-07-2019 |
|
182 |
MAT/PUR/32489-B/19 |
JOCKEY PUMP FOR FIRE WATER SYSTEM |
16-07-2019 |
15-07-2019 |
|
183 |
MAT/PUR/10718-B/19 |
SUPPLY OF HYDROGEN |
06-07-2019 |
05-07-2019 |
|
184 |
MEC30186/2580 |
DESIGN, MANUFACTURE,TESTING AND SUPPLY OF EPDM GASKET FOR ELECTROLYZER CELL |
09-07-2019 |
08-07-2019 |
|
185 |
MAT/PUR/32505/19 |
CS PIPES- NON IBR |
11-07-2019 |
10-07-2019 |
|
186 |
MEC30183/2567 |
OVERHAULING & DYNAMIC BALANCING OF TURBO CHARGER (VTR 454-1-ABB MAKE) |
10-07-2019 |
09-07-2019 |
|
187 |
MEC30183 |
OVERHAULING AND DYNAMIC BALANCING OF TURBO CHARGER |
10-07-2019 |
09-07-2019 |
|
188 |
MEC30183/2567 |
OVERHAULING AND DYNAMIC BALANCING OF TURBO CHARGER (VTR 454-1-ABB MAKE) |
10-07-2019 |
09-07-2019 |
|
189 |
MEC30179/2516 |
PAINTING OF PIPELINES AND STRUTURALS OF H2,N2,PROPYLENE BULLETS AREAS |
23-07-2019 |
22-07-2019 |
|
190 |
MEC30184/2565 |
OVERHAULING AND CALIBRATION OF WOODWARD GOVERNOR TYPE UG 40 D |
26-06-2019 |
26-06-2019 |
|
191 |
MAT/PUR/1072/2019 |
SULPHURIC ACID |
04-07-2019 |
03-07-2019 |
|
192 |
MAT/PUR/10722/2019 |
CAUSTIC SODA LYE |
25-07-2019 |
24-07-2019 |
|
193 |
MAT/PUR/10723/2019 |
BENZENE |
09-07-2019 |
08-07-2019 |
|
194 |
MAT/PUR/10724/2019 |
TRANSPORTATION OF BENZENE |
09-07-2019 |
08-07-2019 |
|
195 |
MAT/PUR/10724/2019 |
TRANSPORTATION OF BENZENE |
09-07-2019 |
08-07-2019 |
|
196 |
MAT/PUR/10724/2019 |
TRANSPORTATION OF BENZENE |
09-07-2019 |
08-07-2019 |
|
197 |
MAT/PUR/10721/2019 |
SULPHURIC ACID |
11-07-2019 |
10-07-2019 |
|
198 |
PAD/2019/00002 DTD.10.07.2019 |
CONTRACT FOF SECURITY ARRANGEMENTS IN HOC TOWNSHIP |
25-07-2019 |
24-07-2019 |
|
199 |
MAT/PUR/32507/19 |
BOILER FURNACE TUBES as per RFQ
NO. 6000022424/2597/32507 attached |
01-08-2019 |
31-07-2019 |
|
200 |
MAT/PUR/32507/2019 |
BOILER FURNANCE TUBES |
01-08-2019 |
31-07-2019 |
|
201 |
PAD/2019/00002 |
SECURITY ARRANGEMENTS IN HOC TOWNSHIP |
25-07-2019 |
24-07-2019 |
|
202 |
MAT/PUR/32476-C/2019 |
CLARIFIED WATER PUMP |
06-08-2019 |
05-08-2019 |
|
203 |
CIV10080/2019 |
REPAIRS TO PIPE RACKS/RCC STRUCTURES IN EVAPORATION SECTION |
07-08-2019 |
06-08-2019 |
|
204 |
HOC/ELE/PLANT/416 |
ARC OF REWINDING AND REPAIR OF LT INDUCTION MOTOR 2019-2020 |
09-08-2019 |
08-08-2019 |
|
205 |
CIV10081/2019 |
PROVIDING/REPLACING BARBED WIRE FENCING AT COMPOUND WALL |
13-08-2019 |
12-08-2019 |
|
206 |
ELE/MRS/334/03/2600 |
MRS YARD STRUCTURAL BOLT REPLACING WORKS |
21-08-2019 |
21-08-2019 |
|
207 |
CIV10079/2019 |
PAINTING OF MRS BUILDING |
16-08-2019 |
14-08-2019 |
|
208 |
HOC/MSS/606/2019/910 |
RENEWAL OF SYMANTEC ANTIVIRUS SOFTWARE |
28-08-2019 |
28-08-2019 |
|
209 |
MEC30187/2605 |
REPAIR AND PAINTING OF CPP STACK AND DERRICK |
28-08-2019 |
27-08-2019 |
|
210 |
CIV10083/2019 |
REPAIRS AND MAINTENANCE OF CANTEEN COOKING AREA |
28-08-2019 |
27-08-2019 |
|
211 |
MAT/PUR/32521/2019 |
MECH SEAL (DURA METALLIC) |
04-09-2019 |
03-09-2019 |
|
212 |
MAT/PUR/32522/2019 |
MECH SEAL (SEALOL) |
04-09-2019 |
03-09-2019 |
|
213 |
HOCL/ELE/PLANT/416 |
ARC OF REWINDING AND REPAIR OF LT INDUCTION MOTORS 2019-2020 |
30-08-2019 |
29-08-2019 |
|
214 |
MAT/PUR/80082-M/2019 |
CS/SS STUD WITH NUT |
30-08-2019 |
29-08-2019 |
|
215 |
MAT/PUR/80081- M |
CS/SS PIPES |
30-08-2019 |
29-08-2019 |
|
216 |
MAT/PUR/70656/2019 |
OXYGEN ANALYSER ZIRCONIA PROBE |
06-09-2019 |
05-09-2019 |
|
217 |
CIV10080/19 |
REPAIRS TO RCC STRUCTURES IN EVAPORATION SECTION- REFLOAT |
07-09-2019 |
06-09-2019 |
|
218 |
MAT/PUR/80083 M/2019 |
CS FLANGES NON IBR |
03-09-2019 |
02-09-2019 |
|
219 |
MEC30185/2566 |
RECONDITIONING OF CPP ENGINE NO 1 |
18-09-2019 |
17-09-2019 |
|
220 |
PAD/2019/00003 |
CANTEEN CONTRACT 2019 |
17-09-2019 |
16-08-2019 |
|
221 |
HOCL/SALE/VADODARA/2019 |
Sale of Office Premises (1700 Sq. ft.) at 3A Kirti Tower Sayajiganj Vadodara on ”AS IS WHERE IS BASIS’’ through open tender |
26-09-2019 |
26-09-2019 |
|
222 |
55555 |
ssssss |
30-08-2019 |
29-08-2019 |
|
223 |
PAD/2019/00003 |
CANTEEN CONTRACT 2019 |
17-09-2019 |
16-09-2019 |
|
224 |
CIV10084/2643/2019 |
CONSTRUCTION OF TOILET, SEPTIC TANK AND SOAK PIT NEAR COOLING TOWER |
28-08-2019 |
28-08-2019 |
|
225 |
HOC/MSS/607/2019-2020 |
AMC FOR LAN FOR THE PERIOD 2019-2020 |
17-09-2019 |
16-09-2019 |
|
226 |
HOCL/Panvel/Valuation/2019-20 dated 26/08/2019 |
Limited Tender Enquiry for appointment of Govt. approved Valuer for valuation of HOCL’s Land Parcel at Panvel |
09-09-2019 |
09-09-2019 |
|
227 |
MAT/PUR/32516/2019 |
COOLING AND BOILER WATER TREATMENT CHEMICALS |
30-08-2019 |
29-08-2019 |
|
228 |
pad/2019/00004 |
HOUSE KEEPING AND WASTE DISPOSAL WORK AT FACTORY |
25-09-2019 |
24-09-2019 |
|
229 |
HOC/MSS/606/2019 |
RENEWAL OF SYMANTEC ANTIVIRUS SOFTWARE |
18-09-2019 |
18-09-2019 |
|
230 |
2650 |
SERVICING AND TESTING OF ABB MAKE SF6 BREAKERS |
20-09-2019 |
20-09-2019 |
|
231 |
MAT/PUR/32523/2019 |
DRIFT ELEMINATOR |
24-09-2019 |
23-09-2019 |
|
232 |
MAT/PUR/10728/2019 |
BENZENE |
12-09-2019 |
11-09-2019 |
|
233 |
Recruitment |
Recruitment of Temporary Medical Officer |
24-09-2019 |
24-09-2019 |
|
234 |
MAT/PUR/10729/2019 |
SULPHURIC ACID |
15-10-2019 |
14-10-2019 |
|
235 |
ELE/H2O2-UTY/541 |
SERVICING AND TESTING OF ABB MAKE SF6 BREAKERS |
09-10-2019 |
09-10-2019 |
|
236 |
MAT/PUR/32535/2019 |
LOADING ARM ASSEMBLY |
16-10-2019 |
15-10-2019 |
|
237 |
MAT/PUR/10731/2019 |
BENZENE |
03-10-2019 |
02-10-2019 |
|
238 |
HOC/MSS/607/2019-2020 |
AMC FOR LAN FOR THE PERIOD 2019-2020 |
03-10-2019 |
02-10-2019 |
|
239 |
PAD/2019/00005 |
CONTRACT FOR ENGAGING SKILLED LABOURERS FOR SHUTDOWN ACTIVITIES |
04-10-2019 |
03-10-2019 |
|
240 |
MEC30194 |
SPECIALIST SERVICES FOR INSPECTION |
01-10-2019 |
30-09-2019 |
|
241 |
PAD/2019/00006 |
HOUSE KEEPING AND WASTE DISPOSAL WORK AT HOC TOWNSHIP |
19-10-2019 |
18-10-2019 |
|
242 |
MAT/PUR/32523-B/2019 |
DRIFT ELEMINATOR |
16-10-2019 |
15-10-2019 |
|
243 |
MAT/PUR/10730/2019 |
CARBOUY |
29-10-2019 |
28-10-2019 |
|
244 |
MAT/PUR/21847/2019 |
FLAME PROOF MOTOR |
02-11-2019 |
01-11-2019 |
|
245 |
MAT/PUR/32539/2019 |
SPARES FOR CPT AIR COMPRESSOR |
01-11-2019 |
31-10-2019 |
|
246 |
MAT/PUR/32535-B/2019 |
LOADING ARM ASSEMBLY |
31-10-2019 |
30-10-2019 |
|
247 |
MAT/PUR/32533/2019 |
STRUCTURAL MATERIALS |
12-11-2019 |
11-11-2019 |
|
248 |
HOC/ELE/H2O2-UTY/542 |
AMC OF TOWNSHIP ELECTRICAL 2019-2020 |
12-11-2019 |
11-11-2019 |
|
249 |
PAD/2019/00007 |
GRASS CUTTING WORKS IN PLANT AND NON PLANT AREAS |
09-11-2019 |
08-11-2019 |
|
250 |
PAD/2019/00007 |
GRASS CUTTING WORK IN PLANT AND NON PLANT AREAS |
09-11-2019 |
08-11-2019 |
|
251 |
MEC30195/2677 |
INSULATION,WRAPPING AND COATING WORK |
01-11-2019 |
31-10-2019 |
|
252 |
MAT/PUR/41659/2019 |
SAFETY SHOES |
19-11-2019 |
18-11-2019 |
|
253 |
MAT/PUR/10734/2019 |
TRANSPORTATION OF SULPHURIC ACID |
05-11-2019 |
04-11-2019 |
|
254 |
CIV10086/2019 |
MISCELLANEOUS CIVIL MAINTENANCE WORKS IN PLANT AND NON PLANT AREAS
2019-2020 |
26-11-2019 |
25-11-2019 |
|
255 |
MEC30196 |
PIPING NON IBR FIRE HYDRANT |
29-11-2019 |
28-11-2019 |
|
256 |
MEC30196 |
PIPING NON IBR FIRE HYDRANT |
29-11-2019 |
28-11-2019 |
|
257 |
MEC30196 |
PIPING NON IBR FIRE HYDRANT |
29-11-2019 |
28-11-2019 |
|
258 |
MAT/PUR/21847-B/2019 |
FLAME PROOF MOTOR |
06-12-2019 |
05-12-2019 |
|
259 |
MAT/PUR/21847-B/2019 |
FLAME PROOF MOTOR |
06-12-2019 |
05-12-2019 |
|
260 |
ELE/H2O2-UTY/543 |
AMC OF MISCELLANEOUS ELECTRICAL WORKS 2019-20 |
18-12-2019 |
18-12-2019 |
|
261 |
PAD/ADMN/TS/2019 |
[Cancelled] Tender for deployment of Security Personnel at Townships at Rasayani & Panvel |
06-12-2019 |
06-12-2019 |
|
262 |
MAT/PUR/10738/19 |
SUPPLY OF BENZENE |
13-12-2019 |
12-12-2019 |
|
263 |
PAD/ADMN/TS/2019 |
Refloating of limited tender for deployment of Security Personnel at
Townships at Rasayani & Panvel. |
18-12-2019 |
18-12-2019 |
|
264 |
MAT/PUR/10740/2019 |
TRANSPORTATION OF BENZENE |
17-12-2019 |
16-12-2019 |
|
265 |
MAT/PUR/10740/2019 |
TRANSPORTATION OF BENZENE |
17-12-2019 |
16-12-2019 |
|
266 |
MEDICLAIM/2019-2020 |
Group Mediclaim Insurance Policy for Retired/VRS Employees & their Spouses and Spouse of deceased employees |
30-12-2019 |
30-12-2019 |
|
267 |
HOC/P&A/MEDICLAIM/2019-2020 |
Group Mediclaim Insurance Policy |
30-12-2019 |
30-12-2019 |
|
268 |
HOC/P&A/MEDICLAIM/2019-2020 |
Group Mediclaim Insurance Policy for Retired/VRS Employees & their Spouses and Spouse of deceased employees |
30-12-2019 |
30-12-2019 |
|
269 |
HOC/P&A/MEDICLAIM/2019-2020 |
Group Mediclaim Insurance Policy |
30-12-2019 |
30-12-2019 |
|
270 |
HOC/P&A/MEDICLAIM/2019-2020 |
Group Mediclaim Insurance Policy for Retired/VRS Employees & their Spouses and Spouse of deceased employees |
30-12-2019 |
30-12-2019 |
|
271 |
MAT/PUR/10745/19 |
Supply of Benzene as per specification
attached. |
27-12-2019 |
26-12-2019 |
|
272 |
MEC30187/2605 |
REPAIR AND PAINTING OF CPP STACK AND DERRICK |
04-01-2020 |
03-01-2020 |
|
273 |
MAT/PUR/10742/19 |
SUPPLY OF CAUSTIC SODA LYE |
14-01-2020 |
13-01-2020 |
|
274 |
MAT/PUR/10743/19 |
SUPPLY OF SULPHURIC ACID |
10-01-2020 |
09-01-2020 |
|
275 |
MEC30198 |
MAINTENANCE OF PRESSURE VESSELS/ACCESSORIES/EQUIPMENTS OF CPP ENGINE |
03-01-2020 |
02-01-2020 |
|
276 |
HOC/MSS/611/2019/1526 |
OPTICAL FIBER CABLE LAYING AND TERMINATION AT OUR FACTORY AT AMBALAMUGAL, KOCHI |
15-01-2020 |
15-01-2020 |
|
277 |
MAT/PUR/10748/2019 |
SHIPPING OF BENZENE |
16-01-2020 |
15-01-2020 |
|
278 |
MAT/PUR/10749/19 |
HIRING OF STORAGE TANK FOR BENZENE |
23-01-2020 |
22-01-2020 |
|
279 |
MAT/PUR/50341/19-20 |
SUPPLY OF 2MCA |
13-02-2020 |
12-02-2020 |
|
280 |
MAT/PUR/50341/19-20 |
SUPPLY OF 2MCA
|
13-02-2020 |
12-02-2020 |
|
281 |
MEC30199 |
PAINTING OF HORTON SPHERE |
11-02-2020 |
10-02-2020 |
|
282 |
MAT/PUR/10747/19 |
SUPPLY OF MS BARRELS |
19-02-2020 |
18-02-2020 |
|
283 |
MAT/PUR/32580/19 |
SUPPLY OF CS STUDS |
28-02-2020 |
27-02-2020 |
|
284 |
CIV10087/2020 |
PROVIDING KUTCHA ROAD AND PATHWAY ALONG THE INSIDE PERIPHERY OF COMPOUND WALL |
25-02-2020 |
24-02-2020 |
|
285 |
MAT/PUR/32581/19-20 |
SUPPLY OF FILTER CANDLE |
12-02-2020 |
11-02-2020 |
|
286 |
MAT/PUR/32581/19-20 |
SUPPLY OF FILTER CANDLE |
12-03-2020 |
11-03-2020 |
|
287 |
MAT/PUR/10755/20 |
SUPPLY OF HM-HDPE CARBOUYS |
13-03-2020 |
12-03-2020 |
|
288 |
CIV10088/2020 |
PROVIDING PARTITION FOR AC CABINS IN ADMINISTRATIVE BUILDING |
24-02-2020 |
24-02-2020 |
|
289 |
FIN/INS/ENQ/2020-21 |
INSURANCE RENEWAL |
18-03-2020 |
17-03-2020 |
|
290 |
FIN/ENQ/2020-21 |
APPOINTMENT OF SYSTEM AUDITOR |
12-03-2020 |
12-03-2020 |
|
291 |
20000033/21867 |
UHF WIRELESS SET |
12-03-2020 |
11-03-2020 |
|
292 |
MEC30179 |
PAINTING OF PIPELINE AND STRUCTURALS |
31-03-2020 |
30-03-2020 |
|
293 |
MEC30179/ 2020_HOCL_458030_3 |
PAINTING OF PIPELINE AND STRUCTURALA OF H2, N2,PROPYLENE, BULLETS AREAS,LPG AREAS, BOILER, HOT OIL AND MRS AREAS |
31-03-2020 |
30-03-2020 |
|
294 |
MR/ISO/2020 |
IMPLEMENTATION OF IMS INTEGRATED MANAGEMENT SYSTEM ISO 9001 AND 14001 AND 45001 ENGAGEMENT OF CERTIFICATION BODY |
23-03-2020 |
21-03-2020 |
|
295 |
MEC30201 |
STENCILING ARROWS,LETTER AND NUMBERS ON EQUIPMENT AND PIPELINES |
19-03-2020 |
18-03-2020 |
|
296 |
MEC30204 (2020_HOCL_549948_1) |
RECONDITIONING OF MECHANICAL SEAL |
27-03-2020 |
26-03-2020 |
|
297 |
MEC30202- 2020_551076_1 |
PAINTING OF PIPING AND EQUIPMENT OF CUMENE, PRU AND TANKAGE AREA |
06-04-2020 |
04-04-2020 |
|
298 |
CIV10090/2020_HOCL_548999_1 |
SUPPLYING AND LAYING PAVING TILES NEAR MAIN GATE |
24-03-2020 |
23-03-2020 |
|
299 |
CIV10091/2020 |
MISCELLANEOUS CIVIL MAINTENANCE WORKS IN HOC TOWNSHIP 2019-2020 |
27-03-2020 |
26-03-2020 |
|
300 |
CIV10092/2020 |
PROVIDING AND LAYING TILES IN HOC TOWNSHIP |
13-03-2020 |
13-03-2020 |
|
301 |
2020_HOCL_551474_1 |
SECURITY ARRANGEMENTS IN FACTORY |
25-03-2020 |
24-03-2020 |
|
302 |
MEC30206/2020 |
SKILLED LABOUR SUPPLY 2020 |
04-04-2020 |
03-04-2020 |
|
303 |
Admn./HV_REQ/2020 |
Providing A/c vehicles on as and when required
basis for official use on Annual Rate Contract basis for a
period of one year. |
31-03-2020 |
31-03-2020 |
|
304 |
MAT/PUR/10758/20 |
SUPPLY OF SULPHURIC ACID |
07-04-2020 |
06-04-2020 |
|
305 |
UTY30141 |
ANNUAL CLEANING AND INSPECTION OF BOILERS - K 479, K 480 & K 607 |
06-05-2020 |
05-05-2020 |
|
306 |
MEC30204 |
RECONDITIONING OF MECHANICAL SEAL - REFLOAT |
29-04-2020 |
28-04-2020 |
|
307 |
MEC30201 |
STENCILING ARROWS, LETTERS AND NUMBERS ON EQUIPMENT AND PIPELINES- REFLOAT |
29-04-2020 |
28-04-2020 |
|
308 |
MEC30202 |
PAINTING OF PIPING AND EQUIPMENT OF CUMENE, PRU AND TANKAGE AREA- REFLOAT |
29-04-2020 |
28-04-2020 |
|
309 |
MR/ISO/2020 |
IMPLEMENTATION OF IMS INTEGRATED MANAGEMENT SYSTEM ISO 9001 AND 14001 AND 45001 ENGAGEMENT OF CERTIFICATION BODY- REFLOAT |
29-04-2020 |
28-04-2020 |
|
310 |
MEC30206 |
SKILLED LABOUR SUPPLY 2020 - REFLOAT |
29-04-2020 |
28-04-2020 |
|
311 |
ELE/H2O2/UTY/546 |
AMC WINDOWS AC, split ac and water cooler 2020-21 |
13-05-2020 |
13-05-2020 |
|
312 |
ELE/PLANT/423 |
AMC OF APFC PANELS 2020-21 |
15-05-2020 |
15-05-2020 |
|
313 |
CIV10091/2020 |
MISCELLANEOUS CIVIL MAINTENANCE WORK IN HOC TOWNSHIP 2019-2020- REFLOAT |
14-05-2020 |
13-05-2020 |
|
314 |
MAT/PUR/21891/20 |
SUPPLY OF MOTOR OPERATING MECHANISM FOR 66 KV ISOLATOR |
21-05-2020 |
20-05-2020 |
|
315 |
MEC30208 |
ERECTION AND REMOVAL OF SCAFFOLDING |
20-05-2020 |
19-05-2020 |
|
316 |
CIVIL/70000021 |
PREEMONSOON MAINTENANCE WORK IN PLANT AND NON PLANT AREAS, CLEANING STORM WATER DRAINS AND ROOF TOPS IN FACTORY |
13-05-2020 |
13-05-2020 |
|
317 |
MAT/PUR/10767/20 |
TRANSPORTATION OF BENZENE |
04-06-2020 |
03-06-2020 |
|
318 |
ELE/PLANT/426/4 |
AMC OF TELEPHONE LINES IN FACTORY AND TOWNSHIP 2020-2021 |
04-06-2020 |
03-06-2020 |
|
319 |
ELE/PLANT/426/4 |
AMC OF TELEPHONE LINES IN FACTORY AND TOWNSHIP 2020-2021 |
04-06-2020 |
03-06-2020 |
|
320 |
PAD/2020/004 |
RENEWAL OF GROUP PERSONAL ACCIDENT (GPA) POLICY 2020-2021 |
05-06-2020 |
04-06-2020 |
|
321 |
MEC30142 2020_HOCL_556728_1 |
ONLINE LEAK SEALING |
20-05-2020 |
19-05-2020 |
|
322 |
HOC/FIN/COST AUDIT/2020-21 |
APPOINTMENT OF COST AUDITORS FOR THE FINANCIAL YEAR 2020-2021 |
29-05-2020 |
29-05-2020 |
|
323 |
MAT/PUR/32568/20 |
BEARINGS
|
16-06-2020 |
15-06-2020 |
|
324 |
HOC/MSS/515/2020 |
डेटा सेंटर के लिए एएमसी
AMC FOR DATA CENTER AT HOCL AMBALAMUGAL |
16-06-2020 |
15-06-2020 |
|
325 |
MAT/PUR/32592/20 |
हीट एक्सचेंजर के लिए एसएस यू ट्यूब
SS U TUBES FOR HEAT EXCHANGER
|
19-06-2020 |
18-06-2020 |
|
326 |
MAT/PUR/32606/2020 |
कूलिंग टॉवर फैन ड्राइव शाफ्ट असम्बेली
COOLING TOWER FAN DRIVE SHAFT ASSEMBLY
|
25-06-2020 |
24-06-2020 |
|
327 |
HOC/MSS/614/2020/423 |
कोची, अंबलमुगल स्थित एचओसीएल फ़ैक्टरी में वीडियो कॉन्फ्रेंसिंग सुविधा लगाने के लिए कोटेशन के लिए अनुरोध (आरएफ़क्यू) संबंधी
RFQ FOR INSTALLATION OF A VIDEO CONFERENCING FACILITY AT HOCL FACTORY AT AMBALAMUGAL, KOCHI |
19-06-2020 |
19-06-2020 |
|
328 |
MAT/PUR/50342/20 |
2 एथिलैंथ्राक्विनन
2 ETHYLANTHRAQUINON
|
30-06-2020 |
29-06-2020 |
|
329 |
PAD/2020/005 |
विविध प्रकार के अनियत कार्य के लिए अकुशल श्रमिकों को लगाने के लिए ठेका CONTRACT FOR ENGAGING UNSKILLED LABOURERS FOR CASUAL JOBS OF MISCELLANEOUS NATURE. |
04-07-2020 |
03-07-2020 |
|
330 |
MEC30214 |
फैक्टरी नियम के तहत दाब वाहिकाओं (प्रेशर वेसल) और पीएसवी की जाँच INSPECTION OF PRESSURE VESSELS AND PSVs UNDER FACTORIES RULE |
02-07-2020 |
01-07-2020 |
|
331 |
MEC30212 |
पाइपिंग और उपस्करों का अल्ट्रासोनिक मोटाई सर्वेक्षण
ULTRASONIC THICKNESS SURVEY OF PIPING AND EQUIPMENTS
|
09-07-2020 |
08-07-2020 |
|
332 |
MEC30212 |
पाइपिंग और उपस्करों का अल्ट्रासोनिक मोटाई सर्वेक्षण
ULTRASONIC THICKNESS SURVEY OF PIPING AND EQUIPMENTS
|
09-07-2020 |
08-07-2020 |
|
333 |
70000032/INST/SPR/2020 |
बॉयलर प्लांट में सेंटम सी एस 3000 का उन्नयन
UPGRADATION OF CENTUM CS 3000 IN BOILER PLANT
|
22-07-2020 |
22-07-2020 |
|
334 |
70000033/INST/SPR/2020/08 |
हाइड्रोजेन परॉक्साइड प्लांट में सेंटम वीपी के डीसीएस (सेंटम सीएस 1000) का उन्नयन
UP-GRADATION OF DCS (CENTUM CS 1000) TO CENTUM VP IN HYDROGEN PEROXIDE PLANT
|
22-07-2020 |
22-07-2020 |
|
335 |
CIV10096/2020 |
कैंटीन के सामने शौचालय ब्लॉक की मरमत्त
REPAIRS TO TOILET BLOCK NEAR CANTEEN
|
21-07-2020 |
20-07-2020 |
|
336 |
MAT/PUR/10772/20 |
सल्फ्यूरिक ऐसिड की आपूर्ति, आईएस-266(1993) के अनुसार, शुद्धता (%w/w) न्यूनतम : 98%
Supply of SULPHURIC ACID, as per IS-266(1993), Purity (%w/w) minimum: 98%
|
28-07-2020 |
27-07-2020 |
|
337 |
MAT/PUR/10773/20 |
बेन्जीन की आपूर्ति संलग्न विनिर्देशों के अनुसार
Supply of Benzene as per specification attached.
|
17-07-2020 |
16-07-2020 |
|
338 |
MEC30211 |
ऊष्म विनिमयक का अनुरक्षण- ई4507 ए/बी (एफ़एसी ओवरहेड कंडेंसर) -वार्षिक दर ठेका
MAINTENANCE OF HEAT EXCHANGER - E 4507 A/B (FAC OVERHEAD CONDENSER ) - ANNUAL RATE CONTRACT
|
30-07-2020 |
29-07-2020 |
|
339 |
MEC30213 |
ऊष्म विनिमयकों का अनुरक्षण (वार्षिक दर ठेका)
MAINTENANCE OF HEAT EXCHANGERS (ANNUAL RATE CONTRACT)
|
30-07-2020 |
29-07-2020 |
|
340 |
HOC/ELE/H2O2-UTY/548 |
एलईडी स्ट्रीट लाइट और फ़्लड लाइट फिक्सचर की स्थापन
Installation of LED Street Light and Flood light fixtures
|
04-08-2020 |
03-08-2020 |
|
341 |
MEC30214-REFLOAT |
फैक्टरी नियम के तहत दाब वाहिकाओं (प्रेशर वेसल) और पीएसवी की जाँच INSPECTION OF PRESSURE VESSELS AND PSVs UNDER FACTORIES RULE |
23-07-2020 |
22-07-2020 |
|
342 |
PAD/2020/006 |
1. अस्थायी कर्मचारियों के लिए नामित जीपीए पॉलिसी
Named GPA Policy for Temporary Employees
2. प्रशिक्षुओं के लिए नामरहित जीपीए पॉलिसी
Unnamed GPA Policy for Apprentices
|
12-08-2020 |
11-08-2020 |
|
343 |
PAD/2020/006 |
1. अस्थायी कर्मचारियों के लिए नामित जीपीए पॉलिसी
Named GPA Policy for Temporary Employees
2. प्रशिक्षुओं के लिए नामरहित जीपीए पॉलिसी
Unnamed GPA Policy for Apprentices
|
12-08-2020 |
11-08-2020 |
|
344 |
MEC30212 |
पाइपिंग और उपस्करों का अल्ट्रासोनिक मोटाई सर्वेक्षण
ULTRASONIC THICKNESS SURVEY OF PIPING AND EQUIPMENTS- REFLOAT
|
29-07-2020 |
28-07-2020 |
|
345 |
PAD/ADMN/TS/2020 |
[Cancelled] Tender for deployment of Security Personnel at Townships at Rasayani & Panvel |
19-08-2020 |
19-08-2020 |
|
346 |
ELE/PLANT/431/4 |
ARC OF REWINDING AND REPAIR OF LT INDUCTION MOTORS 2020-21 |
20-08-2020 |
19-08-2020 |
|
347 |
MEC30218 |
CRITICAL INSPECTION OF PIPING & EQUIPMENTS IN PHENOL PLANT |
14-08-2020 |
13-08-2020 |
|
348 |
MAT/PUR/10776/20 |
CAUSTIC SODA LYE |
26-08-2020 |
25-08-2020 |
|
349 |
PAD/2020/006 |
GPA POLICIES FOR TEMPORARY EMPLOYEES AND APPRENTICES- EXTENSION |
12-08-2020 |
11-08-2020 |
|
350 |
MAT/PUR/10774/2020 |
HIRING OF TEMPO |
20-08-2020 |
19-08-2020 |
|
351 |
CIV10098/2020 |
PAINTING TO MAIN CONTROL ROOM AND TRAINING CENTRE |
26-08-2020 |
25-08-2020 |
|
352 |
MSS/606/2020 |
एक वर्ष के लिए सीमांटेक एंटिवायरस सॉफ्टवेयर (सिमंटेक 12.1 वर्शन-124 लाइसेन्स) का नवीकरण
RENEWAL OF SYMANTEC ANTIVIRUS SOFTWARE (SYMANTEC 12.1 VERSION-124 LICENSES) FOR ONE YEAR
|
26-08-2020 |
26-08-2020 |
|
353 |
MAT/PUR/50342 B/20 |
The supply of 3,000
Kg of 2 ETHYLANTHRAQUINON (2 EAQ) |
25-08-2020 |
24-08-2020 |
|
354 |
MAT/PUR/32614/20 |
सीएस और एसएस वाल्व
CS & SS Valves |
04-09-2020 |
03-09-2020 |
|
355 |
MAT/PUR/10778/20 |
Appointment of C & F agent for the customs clearing & forwarding work connected with the imports/SEZ procurements to
our factory. |
04-09-2020 |
03-09-2020 |
|
356 |
70000039 |
TRANSFORMER OIL FILTRATION |
09-09-2020 |
09-09-2020 |
|
357 |
MEC30214 |
फैक्टरी नियम के तहत दाब वाहिकाओं (प्रेशर वेसल) और पीएसवी की जाँच INSPECTION OF PRESSURE VESSELS AND PSVs UNDER FACTORIES RULE- REFLOAT |
21-08-2020 |
20-08-2020 |
|
358 |
MAT/PUR/41720 |
संलग्न आरएफ़क्यू सं 20000075/41720 के अनुसार धूप नियंत्रित फिल्म
Sun Control Film as per RFQ NO. 20000075/41720
|
04-09-2020 |
03-09-2020 |
|
359 |
MAT/PUR/21922/20 |
SUPPLY OF 55 KW VFD |
11-09-2020 |
10-09-2020 |
|
360 |
UTY30145 |
REFRACTORY REPAIR WORK IN BOILER |
16-09-2020 |
15-09-2020 |
|
361 |
CIV10099 |
PROVIDING AND LAYING ACID PROOF TILES |
28-08-2020 |
28-08-2020 |
|
362 |
UTY30145 |
REFRACTORY REPAIR WORK IN BOILER |
16-09-2020 |
15-09-2020 |
|
363 |
HOC/MSS/607/2020 |
AMC FOR LAN 2020 |
22-09-2020 |
21-09-2020 |
|
364 |
PAD/2020/007 |
CANTEEN CONTRACT 2020 |
22-09-2020 |
21-09-2020 |
|
365 |
PAD/2020/007 |
CANTEEN CONTRACT 2020 |
22-09-2020 |
21-09-2020 |
|
366 |
MAT/PUR/32655/20 |
अनुसार सीएएफ़ एवं संपीडित ऐस्बेस्टोस मुक्त संधि शीट
CAF & Compressed Asbestos Free Jointing Sheet |
18-09-2020 |
17-09-2020 |
|
367 |
MAT/PUR/32655/20 |
अनुसार सीएएफ़ एवं संपीडित ऐस्बेस्टोस मुक्त संधि शीट
CAF & Compressed Asbestos Free Jointing Sheet |
18-09-2020 |
17-09-2020 |
|
368 |
MAT/PUR/32652/20 |
बॉयलर भरण जल पंप और प्रक्रम भरण जल पंप BOILER FEED WATER PUMP & PROCESS FEED WATER PUMP |
22-09-2020 |
21-09-2020 |
|
369 |
MAT/PUR/32626 |
यंत्र एयर कम्प्रेसर –IV के लिए अंतर शीतल और पश्च शीतल Inter Cooler and After Cooler for Instrument Air Compressor - IV |
22-09-2020 |
21-09-2020 |
|
370 |
CIV10100/2020 |
PROVIDING LIGHT ROOFING INN AUXILIARY SUBSTATION |
19-09-2020 |
18-09-2020 |
|
371 |
MAT/PUR/10777/20 |
SUPPLY OF HM-HDPE CARBOUYS |
30-09-2020 |
29-09-2020 |
|
372 |
20000185/32650 |
बॉयलर के480 के लिए मोचक नली
Releaser Tube for Boiler K480 |
01-10-2020 |
30-09-2020 |
|
373 |
20000157/32627 |
आईएसी-III के लिए अंतर शीतल और पश्च शीतल शैल और पूर्ण ट्यूब एसम्ब्ली
Inter Cooler and After Cooler Shell and Tube Assembly Complete for IAC - III |
01-10-2020 |
30-09-2020 |
|
374 |
PAD/2020/010 |
HOUSE KEEPING AND WASTE DISPOSAL AT TOWNSHIP FOR
THE YEAR 2020-2021
|
12-10-2020 |
09-10-2020 |
|
375 |
70000048/ELE |
MISCELLANEOUS ELECTRICAL WORKS 2020 |
25-09-2020 |
25-09-2020 |
|
376 |
PAD/2020/009 |
CONTRACT FOR HOUSEKEEPING AND WASTE DISPOSAL AT FACTORY |
20-10-2020 |
19-10-2020 |
|
377 |
MAT/PUR/21908 |
SUPPLY OF 150AH MRS BATTERY BANK |
15-10-2020 |
14-10-2020 |
|
378 |
MAT/PUR/32649 |
SUPPLY OF CASTABLE REFRACTORIES FOR BOILER K 480 REPAIR WORK |
14-10-2020 |
13-10-2020 |
|
379 |
MAT/PUR/32651/20 |
ND 40 GLOBE VALVES FOR BOILER |
13-10-2020 |
12-10-2020 |
|
380 |
MAT/PUR/32648 |
SS TUBES FOR E4502 |
15-10-2020 |
14-10-2020 |
|
381 |
PAD/2020/008 |
CONTRACT FOR SECURITY ARRANGEMENTS IN HOC TOWNSHIP |
20-10-2020 |
19-10-2020 |
|
382 |
PAD/2020/007 (A) |
CANTEEN CONTRACT 2020-2021 - RETENDER |
12-10-2020 |
10-10-2020 |
|
383 |
MAT/PUR/21941/20 |
2*15 KVA,110V,50Hz UPS SYSTEM |
23-10-2020 |
22-10-2020 |
|
384 |
MEC30224 |
INSULATION, WRAPPING AND COATING WORK |
12-10-2020 |
12-10-2020 |
|
385 |
MEC30224 |
INSULATION,WRAPPING AND COATING WORK |
12-10-2020 |
09-10-2020 |
|
386 |
MAT/PUR/32595 |
SUPPLY OF STRUCTURAL ITEM |
04-11-2020 |
03-11-2020 |
|
387 |
MAT/PUR/10784/20 |
SUPPLY OF SULPHURIC ACID |
28-10-2020 |
27-10-2020 |
|
388 |
HOC/ELE/H2O2-UTY/550 |
AMC OF TOWNSHIP ELECTRICAL 2020-2021 |
05-11-2020 |
04-11-2020 |
|
389 |
HOC/MSS/613/2020-2021 |
RATE CONTRACT FOR REFILLING TONER FOR ONE YEAR |
07-11-2020 |
06-11-2020 |
|
390 |
70000053/ELE/553 |
OIL LEAK ARRESTING OF RECTIFIER TRANSFORMER |
11-11-2020 |
11-11-2020 |
|
391 |
HOC/ISO/001/2020 |
IMPLEMENTATION OF ISO 50001:2018, EnMS |
10-11-2020 |
09-11-2020 |
|
392 |
MEC30223 |
CLEANING OF TUBE BUNDLES BY HYDROBLASTING |
16-11-2020 |
13-11-2020 |
|
393 |
MEC30223 |
CLEANING OF TUBE BUNDLES BY HYDROBLASTING |
16-11-2020 |
13-11-2020 |
|
394 |
MAT/PUR/32642/20 |
CLARIFIED WATER PUMP AND BIO STUDGE PUMP |
19-11-2020 |
18-11-2020 |
|
395 |
MAT/PUR/21908-B/20 |
150AH MRS BATTERY BANK |
27-11-2020 |
26-11-2020 |
|
396 |
PAD/2020/009 A |
HOUSEKEEPING AND WASTE DISPOSAL WORK AT FACTORY |
16-11-2020 |
13-11-2020 |
|
397 |
MAT/PUR/32675/20 |
CS PIPES |
01-12-2020 |
30-11-2020 |
|
398 |
MEC30231 |
SUPPLY, ERECTION AND COMMISSIONING OF INCINERATOR AT HOCL TOWNSHIP |
27-11-2020 |
26-11-2020 |
|
399 |
MAT/PUR/32676/20 |
WASH WATER CIRCULATION PUMP P2004 |
02-12-2020 |
01-12-2020 |
|
400 |
PAD/2020/011 |
GRASS CUTTING WORK IN PLANT AND NON PLANT AREA |
01-12-2020 |
30-11-2020 |
|
401 |
MAT/PUR/21966/2020 |
135 KW FLAME PROOF INDUCTION MOTOR |
09-12-2020 |
08-12-2020 |
|
402 |
MAT/PUR/41766/2020 |
SAFETY ITEMS |
01-12-2020 |
30-11-2020 |
|
403 |
70000064/INSTN/SPR/14 |
ALARM AT CONTROL ROOM FOR RUPTURE DISC INSTALLED ON SPHERES AND BULLETS IN PRU |
09-12-2020 |
09-12-2020 |
|
404 |
HOC/INST/SPR/2020/11 |
SUPPLY INSTALLATION AND COMMISSIONING OF 60 TONS WEIGH BRIDGES |
26-12-2020 |
24-12-2020 |
|
405 |
MAT/PUR/32558 B/2020 |
SPACER COUPLING OF ELECTROLYSER |
08-12-2020 |
07-12-2020 |
|
406 |
PAD/2020/012 |
RENEWAL OF GROUP MEDICLAIM INSURANCE POLICY FOR RETIRED /VRS EMPLOYEES &
THEIR SPOUSES AND SPOUSES OF DECEASED EMPLOYEES FOR THE YEAR 2021-22
|
18-12-2020 |
17-12-2020 |
|
407 |
MAT/PUR/50342 C/20 |
2 ETHYLANTHRAQUINON |
15-01-2021 |
14-12-2020 |
|
408 |
MEC30213 |
MAINTENANCE OF HEAT EXCHANGERS (ANNUAL RATE CONTRACT) |
23-12-2020 |
22-12-2020 |
|
409 |
PAD/2020/008A |
CONTRACT FOR SECURITY ARRANGEMENTS IN HOC TOWNSHIP RETENDER |
28-12-2020 |
26-12-2020 |
|
410 |
CIV10110/2020 |
REPAIRS TO LUNCH ROOM NEAR CONTROL ROOM |
22-12-2020 |
21-12-2020 |
|
411 |
HOCL/ISO/001 (R)/2020 |
IMPLEMENTATION OF ISO 50001 2018 EnMS ENERGY MANAGEMENT SYSTEMS FOR ADVISORY SERVICES |
08-01-2021 |
07-01-2021 |
|
412 |
MAT/PUR/50789/20 |
SPA ( SOLID PHOSPHORIC ACID) CATALYST |
05-01-2021 |
04-01-2021 |
|
413 |
MAT/PUR/21922/20 |
55 KW VFD |
05-01-2021 |
04-01-2021 |
|
414 |
MEC30216 |
CLEANING OF TUBE BUNDLES BY HYDRABLASTING METHOD- ANNUAL RATE CONTRACT |
24-12-2020 |
23-12-2020 |
|
415 |
PAD/2020/011 (A) |
GRASS CUTTING WORK IN PLANT AND NON PLANT AREAS |
26-12-2020 |
24-12-2020 |
|
416 |
MAT/PUR/50342/C/20 |
2 ETHYLANTH RAQUINON 2EAQ |
22-12-2020 |
21-12-2020 |
|
417 |
HOC/ELE/H2O2-UTY/558 |
AMC of Miscellaneous Electrical Works 2020 - 2021 |
22-12-2020 |
21-12-2020 |
|
418 |
MAT/PUR/32695/20 |
INTER COOLER AND AFTER COOLER FOR INSTRUMENT AIR COMPRESSOR- IV |
12-01-2021 |
11-01-2021 |
|
419 |
MAT/PUR/32696/20 |
INTER COOLER AND AFTER COOLER SHELL AND TUBE ASSEMBLY COMPLETE FOR IAC-III |
12-01-2021 |
11-01-2021 |
|
420 |
MAT/PUR/41768/20 |
NON ASBSTOS FIBRE CEMENT ROOFING SHEETS |
13-01-2021 |
12-01-2021 |
|
421 |
MAT/PUR/32642 B/20 |
CLARIFIED WATER PUMP AND BIO SLUDGE PUMP |
14-01-2021 |
13-01-2021 |
|
422 |
MAT/PUR/32676 B/20 |
WASH WATER CIRCULATION PUMP P 2004 |
14-01-2021 |
13-01-2021 |
|
423 |
MAT/PUR/32680/20 |
Mechanical Seal Spares as per RFQ NO. 20000256/32680 and 20000257/32680attached |
08-01-2021 |
07-01-2021 |
|
424 |
MAT/PUR/10792/20 |
SUPPLY OF CUMENE |
05-01-2021 |
04-01-2021 |
|
425 |
MAT/PUR/10793/20 |
HIRING OF STORAGE TANKS FOR STORING CUMENE ( CLASS 'B' PETROLEUM PRODUCTS) FOR 2 MONTHS |
05-01-2021 |
04-01-2021 |
|
426 |
MAT/PUR/10794/21 |
SUPPLY OF SULPHURIC ACID |
20-01-2021 |
19-01-2021 |
|
427 |
CIV10113/2020 |
HIRING OF MECHANICAL EXCAVATOR, TIPPER AND PUMP SET |
22-01-2021 |
21-01-2021 |
|
428 |
CIV10114/2020 |
MISCELLANEOUS CIVIL MAINTENANCE WORK IN PLANT AND NON PLANT AREAS 2020-2021 |
15-01-2021 |
14-01-2021 |
|
429 |
MAT/PUR/21922-B/21 |
55 KW VFD-REFLOAT |
22-01-2021 |
21-01-2021 |
|
430 |
MEC30237 |
TESTING AND CERTIFICATION OF SAFETY VALVES UNDER SMPV (U) RULES 1981 |
22-01-2021 |
21-01-2021 |
|
431 |
MAT/PUR/10792-B/21 |
SUPPLY OF CUMENE |
22-02-2021 |
20-02-2021 |
|
432 |
MAT/PUR/10793-B/21 |
HIRING OF STORAGE TANKS FOR STORING CUMENE (CLASS B PETROLEUM PRODUCT FOR TWO MONTHS |
12-03-2021 |
11-03-2021 |
|
433 |
UTY30147 |
ANNUAL CLEANING AND INSPECTION OF WASTE HEAT BOILERS K616 &K617 |
03-02-2021 |
02-02-2021 |
|
434 |
MAT/PUR/3267 B/21 |
STRUCTURAL ITEMS |
20-01-2021 |
20-01-2021 |
|
435 |
MAT/PUR/32677 B/21 |
STRUCTURAL ITEMS |
20-01-2021 |
20-01-2021 |
|
436 |
MEC30232 |
PAINTING OF PIPE AND STRUCTRURAL OF CROSS COUNTRY PIPELINES |
10-02-2021 |
09-02-2021 |
|
437 |
MAT/PUR/32703/21 |
ACTIVATED ALUMINA FOR INSTRUMENT AIR COMPRESSOR DRIERS 1 &11 |
15-02-2021 |
14-02-2021 |
|
438 |
MAT/PUR/10795/21 |
TRANSPORTATION OF LSFO/FURNANCE OIL FROM BPCL WILLINGTON ISLAND TO HOCL FOR A PERIOD OF THREE MONTHS |
23-01-2021 |
22-01-2021 |
|
439 |
MAT/PUR/32696 B/21 |
SUPPLY OF INTER COOLER AND AFTER COOLER FOR INSTRUMENT AIR COMPRESSOR III |
09-02-2021 |
08-02-2021 |
|
440 |
MAT/PUR/32730/21 |
BUTTERFLY VALVE 16" FOR COOLING WATER |
16-02-2021 |
15-02-2021 |
|
441 |
MAT/PUR/32724/21 |
Fractionation Feed Tank (TK6503) Reprocessing Pump |
02-03-2021 |
01-03-2021 |
|
442 |
MAT/PUR/10792 B/21 |
SUPPLY OF CUMENE |
22-02-2021 |
20-02-2021 |
|
443 |
FIN/INS/ENQ/2021-2021-2022 |
RENEWAL OF INSURANCE POLICIES FOR THE YEAR 2021 2022 |
10-03-2021 |
09-03-2021 |
|
444 |
MAT/PUR/32725/21 |
PRESSURE SAFETY VALVES |
05-03-2021 |
04-03-2021 |
|
445 |
MAT/PUR/10793-B/21 |
HIRING OF STORAGE TANKS FOR STORING CUMENE (CLASS B PETROLEUM PRODUCT FOR TWO MONTHS |
02-03-2021 |
01-03-2021 |
|
446 |
MAT/PUR/10792 B/21 |
SUPPLY OF CUMENE |
09-03-2021 |
08-03-2021 |
|
447 |
PAD/2021/001 |
HIRING OF CAR- HOCL KOCHI |
16-03-2021 |
15-03-2021 |
|
448 |
MAT/PUR/10799/21 |
Supply of Caustic Soda Lye Rayon Grade |
19-03-2021 |
18-03-2021 |
|
449 |
MAT/PUR/10792-B/21 |
SUPPLY OF CUMENE |
09-03-2021 |
08-03-2021 |
|
450 |
MAT/PUR/10793/21 |
HIRING OF STORAGE TANKS FOR STORING CUMENE (CLASS B PETROLEUM PRODUCT FOR TWO MONTHS |
09-03-2021 |
08-03-2021 |
|
451 |
MAT/PUR/10793/21 |
HIRING OF STORAGE TANKS FOR STORING CUMENE (CLASS B PETROLEUM PRODUCT FOR TWO MONTHS |
12-03-2021 |
11-03-2021 |
|
452 |
MAT/PUR/10792-B/21 |
SUPPLY OF CUMENE |
12-03-2021 |
11-03-2021 |
|
453 |
70000071/ele/h2o2-UTY/545 |
AMC OF VFD PANELS 2021-2022 |
16-03-2021 |
16-03-2021 |
|
454 |
MAT/PUR/32735/21 |
NEUTRALISATION AQUEOUS RECYCLE PUMP ASSEMBLY COMPLETE |
26-03-2021 |
25-03-2021 |
|
455 |
CIV10115/2021 |
REPLACING AC SHEETS WITH NON- ASBESTOR FIBER CEMENT ROOFING SHEETS IN PLANT AREAS |
18-03-2021 |
17-03-2021 |
|
456 |
MAT/PUR/32739/21 |
DRIFT ELIMINATORS FOR COOLING TOWER |
06-04-2021 |
05-04-2021 |
|
457 |
MAT/PUR/32737/21 |
SPARES FOR ROLLERS |
06-04-2021 |
05-04-2021 |
|
458 |
MAT/PUR/10801/21 |
SUPPLY OF HM- HDPE CARBOUYS |
09-04-2021 |
08-04-2021 |
|
459 |
MAT/PUR/10793-C/21 |
HIRING STORAGE TANKS FOR STORING CUMENE (CLASS 'B') PETROLEUM PRODUCT FOR TWO MONTHS |
23-03-2021 |
22-03-2021 |
|
460 |
MEC30241 |
SUPPLY, FABRICATION, TESTING AND TRANSPORTATION OF SS 316 CLADDED SHELL AND DISH END OF DEPROPANISER OVERHEAD CONDENSER (E-2004) |
13-04-2021 |
12-04-2021 |
|
461 |
MAT/PUR/10756/21 |
HEAT TRANSFER FLUID |
09-04-2021 |
08-04-2021 |
|
462 |
MAT/PUR/50343/21 |
SUPPLY OF 2 METHYL CYCLO HEXYL ACETATE |
06-04-2021 |
05-04-2021 |
|
463 |
MAT/PUR/50343/21 |
SUPPLY OF 2 METHYL CYCLOHEXYL ACETATE |
06-04-2021 |
05-04-2021 |
|
464 |
MAT/PUR/32745/21 |
CS & SS PIPE FITTINGS |
15-04-2021 |
14-04-2021 |
|
465 |
MAT/PUR/50343/21 |
SUPPLY OF 2 METHYL CYCLO HEXYL ACETATE |
06-04-2021 |
05-04-2021 |
|
466 |
MAT/PUR/50343/21 |
SUPPLY OF 2 MCA |
06-04-2021 |
05-04-2021 |
|
467 |
MAT/PUR/32745/21 |
CS AND SS PIPE FITTINGS |
15-04-2021 |
14-04-2021 |
|
468 |
MAT/PUR/50343/21/ |
SUPPLY OF 2 MCA |
06-04-2021 |
05-04-2021 |
|
469 |
MAT/PUR/32745/21/ |
CS AND SS PIPE FITTINGS |
15-04-2021 |
14-04-2021 |
|
470 |
MAT/PUR/10803/21 |
Supply of CUMENE as per specification
attached. |
14-04-2021 |
13-04-2021 |
|
471 |
MEC30245 |
MAINTENANCE OF COLUMNS |
12-04-2021 |
10-04-2021 |
|
472 |
MEC30246 |
MAINTENANCE OF VESSELS IN CUMENE |
12-04-2021 |
10-04-2021 |
|
473 |
MEC30244 |
MAINTENANCE OF HEAT EXCHANGERS-PRU & CUMENE |
12-04-2021 |
10-04-2021 |
|
474 |
MEC30242 |
CUMENE CATALYST UNLOADING AND LOADING |
12-04-2021 |
09-04-2021 |
|
475 |
MEC30243 |
IN SITU MACHINING OF FLANGES |
17-04-2021 |
16-04-2021 |
|
476 |
UTY30148 |
ANNUAL CLEANING AND INSPECTION OF BOILER K479,K480 & K607 |
22-04-2021 |
21-04-2021 |
|
477 |
MAT/PUR/10804/SD9/21 |
CATALYST SUPPORT BALLS 19MM |
09-04-2021 |
08-04-2021 |
|
478 |
MAT/PUR/32753/SD8/21 |
WIRE MESH AND WINDING WIRE |
13-04-2021 |
12-04-2021 |
|
479 |
MAT/PUR/10793-C/21 |
HIRING OF STORAGE TANK FOR CUMENE AT COCHIN AIRPORT |
07-04-2021 |
06-04-2021 |
|
480 |
ELE/h2o2-UTY/564 |
AMC FOR WINDOW AC, SPLIT AC AND WATER COOLERS 2021-2022 |
23-04-2021 |
23-04-2021 |
|
481 |
70000075/ELE/ |
TRANSFORMER 9 AND 10 OIL LEAK ARRESTING |
16-04-2021 |
16-04-2021 |
|
482 |
M AT/PUR/10803/21 |
SUPPLY OF CUMENE- EXTENDED |
14-04-2021 |
13-04-2021 |
|
483 |
MAT/PUR/10793-C/21 |
HIRING OF STORAGE TANK FOR CUMENE AT COCHIN AIRPORT-EXTENDED |
14-04-2021 |
13-04-2021 |
|
484 |
MAT/PUR/32724/B/21 |
FRACTIONATION FEED TANK (TK6503) REPROCESSING PUMP P4520,P3504,H2SO4 OFF LOADING PUMP ASSEMBLY |
29-04-2021 |
28-04-2021 |
|
485 |
MAT/PUR/32725B/21 |
PRESSURE SAFETY VALVES |
29-04-2021 |
28-04-2021 |
|
486 |
MAT/PUR/32736/21 |
SPARES FOR COOLING TOWER S/E |
29-04-2021 |
28-04-2021 |
|
487 |
PROD/28/2021 |
CLEANING OF RAW EFFLUENT EQUALISATION TANK |
15-04-2021 |
13-04-2021 |
|
488 |
TSS-01/SD-2021 |
CLEANING OF BLOWDOWN CONDENSER FOR HOT WORK |
13-04-2021 |
12-04-2021 |
|
489 |
MAT/PUR/32747/21 |
PROCUREMENT OF CS ERW PIPE |
29-04-2021 |
28-04-2021 |
|
490 |
PROD/28/2021 |
CLEANING OF RAW EFFLUENT EQUALISATION TANK |
15-04-2021 |
13-04-2021 |
|
491 |
MAT/PUR/32747/21 |
PROCUREMENT OF CS ERW PIPE (MAT/PUR/32747/21) |
29-04-2021 |
28-04-2021 |
|
492 |
MAT/PUR/32747/21 |
PROCUREMENT OF CS ERW PIPE as per RFQ NO. 20000379/32747 |
29-04-2021 |
28-04-2021 |
|
493 |
PROD/28/2021 |
CLEANING OF RAW EFFLUENT EQUALISATION TANK (PROD/28/2021) |
15-04-2021 |
13-04-2021 |
|
494 |
TSS-01-2021 |
CLEANING OF BLOW DOWN CONDENSER FOR HOT WORK (TSS-01-2021) |
13-04-2021 |
12-04-2021 |
|
495 |
MEC30259 |
FLARE STACK PAINTING 2021 |
26-04-2021 |
24-04-2021 |
|
496 |
MEC30257 |
ERECTION AND REMOVAL OF SCAFFOLDING |
26-04-2021 |
24-04-2021 |
|
497 |
MEC30256 |
CLEANING OF HOT OIL HEATER TUBES, PREPARATION FOR NDT, INSITU METTALLOGRAPHY & HYDROTEST OF TUBES/ COILS IN POSITION |
19-04-2021 |
17-04-2021 |
|
498 |
MEC30249 |
PIPING WORK NON IBR CS & SS |
20-04-2021 |
19-04-2021 |
|
499 |
MAT/PUR/32774/21 |
PROCUREMENT OF CUTTING AND GRINDING WHEEL |
27-04-2021 |
26-04-2021 |
|
500 |
MAT/PUR/32766/21 |
PROCUREMENT OF STUD WITH TWO NUTS |
23-04-2021 |
22-04-2021 |
|
501 |
MAT/PUR/32741/21 |
PURCHASE OF PRESSURE SAFETY VALVES FOR WASTE HEAT BOILERS |
04-05-2021 |
03-05-2021 |
|
502 |
MAT/PUR/32756/21 |
PROCUREMENT OF CS AND SS SEAMLESS PIPES |
23-04-2021 |
22-04-2021 |
|
503 |
MAT/PUR/10801/21 |
SUPPLY OF HM HDPE CARBOUYS |
17-04-2021 |
16-04-2021 |
|
504 |
MAT/PUR/32763/21 |
PURCHASE OF SS VALVES |
04-05-2021 |
03-05-2021 |
|
505 |
MAT/PUR/10803/21 |
2000-5000 MT OF CUMENE FOR OUR CONSUMPTION-EXTENSION |
16-04-2021 |
15-04-2021 |
|
506 |
MAT/PUR/10793-C/21 |
HIRING OF STORAGE TANK FOR CUMENE AT COCHIN AIRPORT |
16-04-2021 |
15-04-2021 |
|
507 |
MEC30260 |
CLEANING OF CUMENE REACTOR & BLOWDOWN CONDENSER V (2509) INSIDE SURFACES BY HYDROBLASTING |
17-04-2021 |
16-04-2021 |
|
508 |
MAT/PUR/10803/21 |
2000-5000 MT OF CUMENE FOR OUR CONSUMPTION-EXTENSION |
21-04-2021 |
20-04-2021 |
|
509 |
test1012 |
tst tender |
16-04-2021 |
16-04-2021 |
|
510 |
MEC30260 |
CLEANING OF CUMENE REACTOR & BLOWDOWN CONDENSER V (2509) INSIDE SURFACES BY HYDROBLASTING |
19-04-2021 |
17-04-2021 |
|
511 |
MAT/PUR/10803/21 |
2000-5000 MT OF CUMENE FOR OUR CONSUMPTION-EXTENSION |
21-04-2021 |
20-04-2021 |
|
512 |
MAT/PUR/10756/21 |
SUPPLY OF HEAT TRANSFER FLUID -TERMS AND CONDITIONS |
17-04-2021 |
16-04-2021 |
|
513 |
MAT/PUR/10793-C/21 |
HIRING OF STORAGE TANK FOR CUMENE AT COCHIN AIRPORT- EXTENSION |
21-04-2021 |
20-04-2021 |
|
514 |
MEC30255 |
CLEANING OF COOLING TOWER |
20-04-2021 |
19-04-2021 |
|
515 |
MAT/PUR/50343-B/21 |
SUPPLY OF 2 METHYL CYCLO HEXYL ACETATE |
20-04-2021 |
19-04-2021 |
|
516 |
MEC30253 |
REPAIR OF STRUCTURAL PLATFORMS |
23-04-2021 |
22-04-2021 |
|
517 |
MEC30251 |
INSULATION, WRAPPING AND COATING WORK |
26-04-2021 |
24-04-2021 |
|
518 |
70000079/MEC/21 |
TREVI TESTING OF PRESSURE SAFETY VALVES |
26-04-2021 |
26-04-2021 |
|
519 |
MEC30252 |
SKILLED LABOUR SUPPLY 2021 |
27-04-2021 |
26-04-2021 |
|
520 |
70000080/MEC30254 |
IN SITU METALLOGRAPHY |
26-04-2021 |
26-04-2021 |
|
521 |
MEC30247 |
CRITICAL INSPECTION OF PIPING & EQUIPMENTS |
26-04-2021 |
24-04-2021 |
|
522 |
MEC30248 |
VALVES REPAIRING, OVERHAULING AND SERVICING |
26-04-2021 |
24-04-2021 |
|
523 |
MAT/PUR/10801 B/21 |
SUPPLY OF HM HDPE CARBOUYS |
04-05-2021 |
03-05-2021 |
|
524 |
MAT/PUR/10812/21 |
SUPPLY OF HM HDPE CARBOUYS |
04-05-2021 |
03-05-2021 |
|
525 |
MAT/PUR/10803 B/21 |
SUPPLY OF CUMENE |
04-05-2021 |
03-05-2021 |
|
526 |
MEC30265 |
FABRICATION/REPAIR/ERECTION AND TESTING OF HDPE PIPING IN THE PLANT |
12-05-2021 |
11-05-2021 |
|
527 |
MEC30264 |
CLEANING PIPELINES IN CUMENE PLANT BY HYDROBLASTING |
12-05-2021 |
11-05-2021 |
|
528 |
MEC30266 |
RADIOGRAPHY FOR PIPELINES |
12-05-2021 |
11-05-2021 |
|
529 |
MAT/PUR/0803 B/21 |
SUPPLY OF CUMENE |
11-05-2021 |
10-05-2021 |
|
530 |
MAT/PUR/10803/21 |
SUPPLY OF CUMENE |
11-05-2021 |
10-05-2021 |
|
531 |
HOC/FIN |
Appointment of Internal Auditors for the F.Y.2021-22 |
25-05-2021 |
25-05-2021 |
|
532 |
MAT/PUR/10803 B/21 |
SUPPLY OF CUMENE 2000-5000 MT |
14-05-2021 |
13-05-2021 |
|
533 |
MEC30267 |
REFRACTORY REPAIR WORK IN HOT OIL HEATER |
25-05-2021 |
24-05-2021 |
|
534 |
MAT/PUR/32736 B/21 |
SPARES FOR COOLING TOWER S/E |
08-06-2021 |
07-06-2021 |
|
535 |
MEC30269 |
RETUBING OF TAR COLUMN REBOILER E 4509 |
15-06-2021 |
14-06-2021 |
|
536 |
PAD/2021/002 |
RENEWAL OF GROUP PERSONAL ACCIDENT (GPA) POLICY FOR THE YEAR 2021-2022 |
15-06-2021 |
14-06-2021 |
|
537 |
MAT/PUR/10815/21 |
SUPPLY OF SULPHURIC ACID |
08-06-2021 |
07-06-2021 |
|
538 |
MAT/PUR/10815/21 |
GeM BID FOR SULPHURIC ACID |
05-06-2021 |
05-06-2021 |
|
539 |
MAT/PUR/32781/21 |
PROCUREMENT OF INSULATION MATERIALS |
15-06-2021 |
14-06-2021 |
|
540 |
MAT/PUR/32740/21 |
PROCUREMENT OF CS SEAMLESS |
22-06-2021 |
21-06-2021 |
|
541 |
MAT/PUR/10813/21 |
GeM BID FOR STEEL BARRELS DRUMS |
05-06-2021 |
05-06-2021 |
|
542 |
MEC30269 |
RETUBING OF TAR COLUMN REBOILER (E-4509) -REFLOAT |
15-06-2021 |
14-06-2021 |
|
543 |
CIV10115/2021 |
REPLACING AC SHEETS WITH NON ASBESTOS FIBER CEMENT ROOFING SHEETS IN PLANT AREAS -REFLOAT |
26-06-2021 |
25-06-2021 |
|
544 |
CIV10125/2021 |
MISCELLANEOUS CIVIL MAINTENANCE WORKS IN HOC TOWNSHIP 2021-2022 |
16-06-2021 |
15-06-2021 |
|
545 |
MEC30271 |
PREPARATORY WORKS FOR STATUTORY INSPECTION OF H2 AND N2 BULLETS UNDER SMPV (U) RULES 1981 |
02-07-2021 |
01-07-2021 |
|
546 |
MEC30272 |
STATUTORY INSPECTION OF H2 AND N2 BULLETS UNDER SMPV (U) RULES 1981 |
02-07-2021 |
01-07-2021 |
|
547 |
MAT/PUR/10816/21 |
TRANSPORTATION OF BENZENE FROM VARIOUS SOURCES AS BELOW TO HOCL AMBALAMUGAL |
03-07-2021 |
02-07-2021 |
|
548 |
70000095/ELE |
REPAIR OF PHENOL TRANSFORMER 2 |
18-06-2021 |
18-06-2021 |
|
549 |
MEC30276 |
REPAIR OF STRUCTURAL PLATFORM |
24-06-2021 |
23-06-2021 |
|
550 |
GEM/2021/B/1292276/ |
MS BARRELS |
28-06-2021 |
28-06-2021 |
|
551 |
MEC30275 |
RETUBING OF CUMENE COLUMN PRODUCT TRIM COOLER E 2013 |
23-06-2021 |
22-06-2021 |
|
552 |
GEM/2021/B/1297563 |
TRANSPORTATION OF BENZENE FROM BPCL MAHUL REFINERY TO MUMBAI TO HOCL AMBALAMUGAL |
03-07-2021 |
03-07-2021 |
|
553 |
GEM/2021/B/1297460 |
TRANSPORTATION OF BENZENE FROM IOCL PANIPAT TO HOCL AMBALAMUGAL |
03-07-2021 |
03-07-2021 |
|
554 |
GEM/2021/B/1294752 |
TRANSPORTATION OF BENZENE FROM OMPL MANGALORE TO HOCL AMBALAMUGAL |
03-07-2021 |
03-07-2021 |
|
555 |
GEM/2021/B/1297460 |
Transportation of Benzene from IOCL Panipat to HOCL Ambalamugal
|
09-07-2021 |
09-07-2021 |
|
556 |
GEM/2021/B/1297563 |
TRANSPORTATION OF BENZENE FROM BPCL MAHUL- MUMBAI TO HOCL AMBALAMUGAL |
09-07-2021 |
09-07-2021 |
|
557 |
GEM/2021/B/1294752 |
TRANSPORTATION OF BENZENE FROM OMPL MANGALORE TO HOCL AMBALAMUGAL |
09-07-2021 |
09-07-2021 |
|
558 |
MAT/PUR/32724C/21 |
FRACTIONATION FEED TANK (TK 6503) REPROCESSING |
21-07-2021 |
19-07-2021 |
|
559 |
MAT/PUR/32737 B/21 |
PROCUREMENT OF SPARES FOR ROLLERS |
21-07-2021 |
19-07-2021 |
|
560 |
MAT/PUR/41807/21 |
Procurement of Server for TALLY ERP 9.0 |
27-07-2021 |
26-07-2021 |
|
561 |
MAT/PUR/10816/21 |
TRANSPORTATION OF BENZENE FOR VARIOUS SOURCES |
09-07-2021 |
08-07-2021 |
|
562 |
HOC/MSS/619/2021 |
SUPPLY,INSTALLATION AND COMMISSIONING OF OUTDOOR LED DISPLAY BOARD |
03-08-2021 |
03-08-2021 |
|
563 |
HOC/INST/SPR/2021/05 |
THE DISPOSAL OF NUCLEONIC LEVEL GAUGE |
30-07-2021 |
29-07-2021 |
|
564 |
GEM/2021/B/1353058 |
DISPLAY BOARD |
03-08-2021 |
03-08-2021 |
|
565 |
HOC/MSS/619/2021 |
SUPPLY,INSTALLATION AND COMMISSIONING OF OUTDOOR LED DISPLAY BOARD |
03-08-2021 |
03-08-2021 |
|
566 |
MAT/PUR/32807/21/GEM/2021/B/1377710 |
STRUCTURAL ITEMS |
02-08-2021 |
02-08-2021 |
|
567 |
MSS/337/2021/GEM/2021/B/1376882 DT.22.07.2021 |
AMC PRINTER 2021 |
05-08-2021 |
05-08-2021 |
|
568 |
GEM/2021/B/1377666 |
CS & SS VALVES |
02-08-2021 |
02-08-2021 |
|
569 |
MAT/PUR/32793/21 |
TEFLON FILTER CLOTH FOR REACTOR FILTER |
13-08-2021 |
13-08-2021 |
|
570 |
MAT/PUR/32788/21/GEM/2021/B/1381057 DT.24.07.2021 |
SHIM PLATES |
03-08-2021 |
03-08-2021 |
|
571 |
MAT/PUR/70706/21-GEM/2021/B/1395736 |
SULPHURIC ACID ANALYSER |
09-07-2021 |
09-07-2021 |
|
572 |
MAT/PUR/70706/21(GEM/2021/B/1395763) |
SULPHURIC ACID ANALYSER |
09-08-2021 |
09-08-2021 |
|
573 |
GEM/2021/B/1390455 |
VACUUM CIRCUIT BREAKER
SERVICE |
07-08-2021 |
07-08-2021 |
|
574 |
GEM/2021/B/1379688 |
EXTERNAL SAFETY AUDIT 2021 |
18-08-2021 |
18-08-2021 |
|
575 |
MAT/PUR/32795/21/GEM/2021/B/1400734 DT.31.07.2021 |
Water Treatment Chemicals |
20-08-2021 |
20-08-2021 |
|
576 |
MAT/PUR/32795/21/2021_HOCL_641199_1 DT 30.07.2021 |
Water Treatment Chemicals
NIC-TENDER
|
19-08-2021 |
19-08-2021 |
|
577 |
PAD/2021/003 |
Tender for GPA
|
03-09-2021 |
03-09-2021 |
|
578 |
GEM/2021/B/1443213 // MAT/PUR/41854/21 |
CLEAN AGENT FIRE EXTINGUISHER |
03-09-2021 |
03-09-2021 |
|
579 |
MAT/PUR/70706/21 GEM/2021/B/1480657 d- 01.09.2021 |
ONLINE SULPHURIC ACID ANALYSER |
11-09-2021 |
11-09-2021 |
|
580 |
MAT/PUR/32797/21 || GEM/2021/B/1483299 |
HIGH SPEED ALL GEARED PRECISION LATHE MACHINE. |
13-09-2021 |
13-09-2021 |
|
581 |
HOC/MSS/606/2021/GEM/2021/B/1496922 |
RENEWAL AND SUPPORT FOR SYMANTEC ANTIVIRUS SOFTWARE |
22-09-2021 |
22-09-2021 |
|
582 |
MAT/PUR/32816/21/GEM/2021/B/1498220 |
STUD WITH 2 NUTS |
17-09-2021 |
17-09-2021 |
|
583 |
MAT/PUR/32817/21/GEM/2021/B/1498803 |
CS & SS VALVES |
17-09-2021 |
17-09-2021 |
|
584 |
MAT/PUR/32826/21(GEM/2021/B/151210) |
COMPLETE TRAY ASSEMBLY(1-14) SIEVE TRAY SINGLE PASS FOR C-2004 |
24-09-2021 |
24-09-2021 |
|
585 |
MAT/PUR/32788/21 |
SHIM PLATES |
02-10-2021 |
01-10-2021 |
|
586 |
CIV10129 |
PROVIDING LIGHT ROOFING FOR TRANSFORMERS IN AUXILIARY SUBSTATION AND H2O2 UTILITY SUBSTATION |
24-09-2021 |
23-09-2021 |
|
587 |
MAT/PUR/32802/21 GEM/2021/B/1527124 |
THIRD PARTY INSPECTION |
28-09-2021 |
28-09-2021 |
|
588 |
MEC30289 |
ULTRASONIC THICKNESS SURVEY OF PIPING AND EQUIPMENTS |
07-10-2021 |
06-10-2021 |
|
589 |
PAD/2021/005 |
HOUSE KEEPING AND WASTE DISPOSAL AT TOWNSHIP FOR
THE YEAR 2021-2022 |
06-10-2021 |
05-10-2021 |
|
590 |
PAD/2021/006 |
CANTEEN CONTRACT 2021-2022 |
13-10-2021 |
12-10-2021 |
|
591 |
MAT/PUR/10821/21(GEM/2021/B/1534858) |
SULPHURIC ACID |
30-09-2021 |
30-09-2021 |
|
592 |
MEC30293 |
PAINTING OF PIPING, EQUIPMENTS AND STRUCTURALS IN CUMOX, MAIN TANK FARM & PTP |
21-10-2021 |
20-10-2021 |
|
593 |
2021_HOCL_650191_1 |
AMC LAN 2021_REFLOAT |
06-10-2021 |
06-10-2021 |
|
594 |
HOC/MSS/606 |
ANTIVIRUS RENEWAL_REFLOAT |
01-10-2021 |
01-10-2021 |
|
595 |
GEM/2021/B/1529540 |
DISPLAY BOARD_REFLOAT |
01-10-2021 |
01-10-2021 |
|
596 |
MAT/PUR/10821/ |
SUPPLY OF SULPHURIC ACID |
08-10-2021 |
07-10-2021 |
|
597 |
MEC30273 |
FRP LINING |
21-10-2021 |
21-10-2021 |
|
598 |
MEC30294 |
STENCILING OF ARROWS,LETTERS AND NUMBERS ON EQUIPMENTS AND PIPELINES |
21-10-2021 |
21-10-2021 |
|
599 |
MAT/PUR/10812/21(GEM/2021/B/1581522) |
SUPPLY OF HM_HDPE CARBOUYS |
29-10-2021 |
28-10-2021 |
|
600 |
MAT/PUR/32824/21(GEM/2021/B/1596875) |
FRACTIONATION FEED TANK REPROCESSING PUMP ASSEMBLY |
25-10-2021 |
25-10-2021 |
|
601 |
MAT/PUR/32824/21(GEM/2021/B/1596553) |
AMS COLUMN OVERHEAD AQUEOUS PUMP |
25-10-2021 |
25-10-2021 |
|
602 |
MAT/PUR/32824/21(GEM/2021/B/1596711) |
RAW EFFLUENT TRANSFER PUMP FOR ETP |
25-10-2021 |
25-10-2021 |
|
603 |
MEC30291 |
FIRE HYDRANT PIPING REPLACEMENT WORK |
10-11-2021 |
10-11-2021 |
|
604 |
MAT/PUR/10822/21 |
CITRIC ACID |
03-11-2021 |
02-11-2021 |
|
605 |
MEC30297 |
DE-COMMISSIONING OF CPP STACK NO.1 |
09-11-2021 |
08-11-2021 |
|
606 |
CIV10131 |
REMOVAL OF BLACK COLOURED WATER FROM HOLDING POND |
01-11-2021 |
01-11-2021 |
|
607 |
MAT/PUR/50344/21 |
2 ETHYL ANTHRA QUINON |
16-11-2021 |
15-11-2021 |
|
608 |
ELE/H2O2/UTY/572 |
AMC OF PACKAGE AC SYSTEM AT H2O2 PLANT |
20-11-2021 |
20-11-2021 |
|
609 |
HOC/ELE/PLANT/449 |
REVAMPING OF FIRE ALARM SYSTEM |
12-11-2021 |
12-11-2021 |
|
610 |
MAT/PUR/50345/21 |
SUPPLY OF 2 METHYL CYCLO HEXYL ACETATE (2MCA) |
24-11-2021 |
23-11-2021 |
|
611 |
MAT/PUR/70728/21 |
PROCUREMENT OF METAL SEATED DOUBLE FLANGED BUTTERFLY VALVES |
30-11-2021 |
29-11-2021 |
|
612 |
MAT/PUR/32812/21 |
PROCUREMENT OF CS & SS GATE & GLOBE VALVES |
25-11-2021 |
24-11-2021 |
|
613 |
MAT/PUR/10826/21 |
Appointing C & F Agent for the Customs Clearing And Forwarding Work for Kochi/Mangalore for a period of 2 years. |
27-11-2021 |
26-11-2021 |
|
614 |
MAT/PUR/32724/21-GEM/2021/B/1654088/21 |
SULPHURIC ACID OFF LOADING PUMP ASSEMBLY |
17-11-2021 |
17-11-2021 |
|
615 |
MEC30298 |
INSULATION WORKS 2021 |
25-11-2021 |
24-11-2021 |
|
616 |
MAT/PUR/32852/21(GEM/2021/1654042) |
MECHANICAL SEAL SPARES FOR PUMPS |
17-11-2021 |
17-11-2021 |
|
617 |
MAT/PUR/10826-GEM/2021/B/1660240 |
APPOINTING C AND F AGENT FOR THE CUSTOMS
CLEARING AND FORWARDING WORK FOR A PERIOD OF 2
YEARS |
27-11-2021 |
27-11-2021 |
|
618 |
PAD/2021/009 |
GRASS CUTTING WORK IN PLANT AREAS |
24-11-2021 |
23-11-2021 |
|
619 |
HOC/MSS/601/2021 |
AMC CCTV 2021-2022 |
02-12-2021 |
02-12-2021 |
|
620 |
MAT/PUR/10823 B/21 |
SUPPLY OF NITRIC ACID 58 - 60% CONCENTRATION |
17-11-2021 |
17-11-2021 |
|
621 |
MAT/PUR/41878/21-GEM/2021/B/1666508 |
PLASTIC SEALS WITH HOC MONOGRAM FOR SEALING FINISHED PRODUCTS TANKERS AFTER FILLING |
23-11-2021 |
23-11-2021 |
|
622 |
MAT/PUR/32793/21 GEM/2021/B/1671702 |
TEFLON FILTER CLOTH FOR REACTOR FILTER |
23-11-2021 |
23-11-2021 |
|
623 |
P&A/2021/010 |
GRASS CUTTING WORK IN NON-PLANT AREA 2022 |
01-12-2021 |
01-12-2021 |
|
624 |
MAT/PUR/32859 |
SUPPLY OF SPARES FOR HOT OIL HEAT BURNER |
26-11-2021 |
26-11-2021 |
|
625 |
MAT/PUR/70731/21 GEM/2021/B/1704619 |
Supply of Acid Control Valve 0.5" Tag no FCV 3504/FCV 3507 |
06-12-2021 |
06-12-2021 |
|
626 |
MAT/PUR/50344 B/21 |
2 ETHYL ANTHRA QUINON ( 2 EAQ) |
08-12-2021 |
08-12-2021 |
|
627 |
MEC30301 |
SKILLED LABOUR SUPPLY |
16-11-2021 |
15-11-2021 |
|
628 |
MEC30301 |
SKILLED LABOUR SUPPLY |
16-12-2021 |
15-12-2021 |
|
629 |
ELE/H2O2-UTY/573 |
LED LIGHT FIXTURE INSTALLATION WORKS PHASE II |
22-12-2021 |
22-12-2021 |
|
630 |
MEC30303 |
SUPPLY, FABRICATION, TESTING AND TRANSPORTATION OF TAR COLUMN OVER HEAD RECEIVER V 4503 |
27-12-2021 |
25-12-2021 |
|
631 |
MAT/PUR/10829/21 |
Supply of Caustic Soda Lye Rayon Grade conforming
to IS-252-2013 (Latest) with consistent concentration
of 31 to 49 % NaOH basis |
06-01-2022 |
05-01-2022 |
|
632 |
MSS/613/2022 |
RATE CONTRACT FOR TONER REFILLING FOR ONE YEAR |
13-01-2022 |
12-01-2022 |
|
633 |
MAT/PUR/32824/21(GEM/2021/B/1812260) |
AMS COLUMN OVERHEAD AQUEOUS PUMP |
10-01-2022 |
10-01-2022 |
|
634 |
MAT/PUR/32875/21 (GEM/2021/B/1816339) |
SUPPLY OF RAW EFFLUENT TRANSFER PUMP FOR ETP |
11-01-2022 |
11-01-2022 |
|
635 |
MAT/PUR/50345-B/21 |
SUPPLY OF 2 METHYL CYCLO HEXYL ACETATE (2MCA) |
13-01-2022 |
12-01-2022 |
|
636 |
MAT/PUR/32860/21 |
SUPPLY OF BEARINGS |
29-01-2022 |
28-01-2022 |
|
637 |
MAT/PUR/32877/22 (GEM/2021/B/1842007) |
SUPPLY OF AMA/PARKER/PALL FILTER |
19-01-2022 |
19-01-2022 |
|
638 |
70000127(GEM/2022/B/1829957) |
HYDROTESTING, SERVICING AND PAINTING OF DCP EXTINGUISHERS OF CAPACITIES 10 KG,25KG,50 KG AND 75 KG |
28-01-2022 |
28-01-2022 |
|
639 |
HOCL/MKD/HP-6%/2021-22 |
APPOINMENT OF DISTRICT LEVEL DISTRIBUTORS FOR HOCL HYDROGEN PEROXIDE-6% |
11-02-2022 |
10-02-2022 |
|
640 |
MAT/PUR/50344 C/21 |
2 ETHYL ANTHRA QUINONE ( 2 EAQ)
|
01-02-2022 |
31-01-2022 |
|
641 |
MEC3036 |
REPAIR OF STRUCTURAL PLATFORMS |
10-02-2022 |
09-02-2022 |
|
642 |
CIV10133 |
REPLACING DAMAGED GI WATERLINE TO HOC TOWNSHIP |
09-02-2022 |
08-02-2022 |
|
643 |
MRKT/FPS/01/22-24 |
Transportation of Hydrogen peroxide in bulk |
23-02-2022 |
22-02-2022 |
|
644 |
MAT/PUR/32824 |
AMS COLUMN OVERHEAD AQUEOUS RECYCLING PUMP ASSEMBLY |
22-02-2022 |
21-02-2022 |
|
645 |
MAT/PUR/32824 |
PROCUREMENT OF AMS COLUMN OVERHEAD AQUEOUS PUMP ASSEMBLY |
22-02-2022 |
21-02-2022 |
|
646 |
MSS/625/2022 |
IT SECURITY AUDIT INCLUDING VULNERABILITY ASSESSMENT PENETRATION TEST FOR NETWORKED IT INFRASTRUCTURE OF HOCL |
23-02-2022 |
23-02-2022 |
|
647 |
MAT/PUR/32824/21 |
AMS COLUMN OVERHEAD AQUEOUS RECYCLING PUMP ASSEMBLY |
22-02-2022 |
21-02-2022 |
|
648 |
PAD/2022/001 |
CONTRACT FOR ENGAGING MARKETING OFFICERS |
21-02-2022 |
21-02-2022 |
|
649 |
MKD/FPS/HP 6 EOI/21-22/107 |
INVITATION FOR EXPRESSION OF INTEREST FOR DISTRICT LEVEL DISTRIBUTORS FOR HOCL HYDROGEN PEROXIDE-6% |
22-02-2022 |
21-02-2022 |
|
650 |
MAT/PUR/10836/21(GEM/2022/B/1942859) |
MS BARRELS |
25-02-2022 |
25-02-2022 |
|
651 |
70000131 |
AMC OF VFD PANELS 2022-23 |
09-03-2022 |
09-03-2022 |
|
652 |
MAT/PUR/32863 C/22 |
PROCUREMENT OF LSHS TRANSFER PUMP FOR HOT OIL |
10-03-2022 |
09-03-2022 |
|
653 |
UTY30150 (GEM/2022/B/1970286) |
ANNUAL CLEANING AND INSPECTION OF BOILER K 479,K480 &K607 |
15-03-2022 |
14-03-2022 |
|
654 |
MEC30311 |
RE-DESIGN, SUPPLY, FABRICATION, TESTING AND TRANSPORTATION OF SHELL AND
DISH END OF RERUN COLUMN REBOILER |
15-03-2022 |
14-03-2022 |
|
655 |
MEC30307 |
MAINTENANCE OF HEAT EXCHANGERS- ANNUAL RATE CONTRACT |
05-03-2022 |
04-03-2022 |
|
656 |
MEC30309 |
CRITICAL INSPECTION OF PIPING AND EQUIPMENTS IN PHENOL
PLANT |
10-03-2022 |
09-03-2022 |
|
657 |
MEC30308 |
AMC FOR ELLIOTT COMPRESSOR |
11-03-2022 |
10-03-2022 |
|
658 |
MRKT/FPS/01/22-24/REFLOAT |
TRANSPORATION OF HYDROGEN PEROXIDE IN ROAD TANKERS |
18-03-2022 |
17-03-2022 |
|
659 |
PAD/2022/002 |
INSURANCE POLICIES |
17-03-2022 |
16-03-2022 |
|
660 |
MEC30312 |
PIPING WORK NON IBR M(CS & SS) |
16-03-2022 |
15-03-2022 |
|
661 |
MAT/PUR/32881/22 (GEM/2022/B/2015655) |
PROCUREMENT OF RERUN COLUMN BOTTOM PUMP (P-5504) & OVERHEAD
PUMP (P-5505) COMPLETE ASSEMBLY |
29-03-2022 |
28-03-2022 |
|
662 |
MAT/PUR/32882/22 |
ROCUREMENT WASH WATER CIRCULATION PUMP (P-2004) COMPLETE
ASSEMBLY |
29-03-2022 |
28-03-2022 |
|
663 |
PAD/2022/003 |
SECURITY ARRANGEMENTS IN FACTORY |
22-03-2022 |
22-03-2022 |
|
664 |
UTY30151 |
REFRACTORY REPAIR WORK IN BOILER - K 479, K 480 & K 607 |
29-03-2022 |
28-03-2022 |
|
665 |
MEC30313 |
IN-SITU MACHINING OF FLANGES
|
02-04-2022 |
01-04-2022 |
|
666 |
MEC30314 |
SERVICING & RECONDITIONING OF FILTER CANDLES |
02-04-2022 |
01-04-2022 |
|
667 |
MEC30316 |
FABRICATION AND ASSEMBLING OF CAC OVERHEAD CONDENSER (E 4502) TUBE BUNDLE |
07-04-2022 |
06-04-2022 |
|
668 |
MAT/PUR/10822 B/21 |
CITRIC ACID FOOD GRADE (4000KG) |
29-03-2022 |
28-03-2022 |
|
669 |
MAT/PUR/32887/22 |
Complete pump assembly of Clarified Water Pump. |
12-04-2022 |
11-04-2022 |
|
670 |
MAT/PUR/32894/22 |
Structural Items For Tar Cracking Modification And DIPB Distillation |
01-04-2022 |
31-03-2022 |
|
671 |
MAT/PUR/10822 B/21 |
CITRIC ACID FOOD GRADE (4000KG) |
29-03-2022 |
28-03-2022 |
|
672 |
MAT/PUR/10822 B/21 |
CITRIC ACID FOOD GRADE (4000KG) |
29-03-2022 |
28-03-2022 |
|
673 |
HOC/FIN/COST AUDIT/2022-23 |
Appointment of Cost Auditors for the Financial Year 2022-23 (Revised) |
04-05-2022 |
04-05-2022 |
|
674 |
MAT/PUR/32893/22 |
Valves For Tar Cracking Modification And DIPB Distillation. |
12-04-2022 |
11-04-2022 |
|
675 |
MAT/PUR/32895/22 |
SUPPLY OF CS AND SS PIPES FOR TAR CRACKING MODIFICATION AND DIPB DISTILLATION. |
04-04-2022 |
04-04-2022 |
|
676 |
MAT/PUR/10841/22 |
Procurement of Monosodium Phosphate Monohydrate (2000KG) |
14-04-2022 |
13-04-2022 |
|
677 |
70000141 |
Painting of main transformer. |
06-04-2022 |
06-04-2022 |
|
678 |
MEC30320 |
PAINTING OF PIPING AND STRUCTURAL |
19-04-2022 |
18-04-2022 |
|
679 |
MEC30315 |
MAINTENANCE OF COLUMNS IN PHENOL PLANT |
20-04-2022 |
19-04-2022 |
|
680 |
MEC30318 |
MAINTENANCE OF HEAT EXCHANGERS AND VESSELS - FRACTIONATION AND TAR CRACKING UNIT |
20-04-2022 |
19-04-2022 |
|
681 |
MAT/PUR/32893 B/22 |
Valves for Tar cracking modification & DIPB Distillation |
12-04-2022 |
11-04-2022 |
|
682 |
CIV10136/2022 |
PRE-MONSOON MAINTENANCE WORK IN PLANT AND NON PLANT AREAS,
CLEANING STORM WATER DRAINS AND ROOFTOPS IN FACTORY 2022-2023 |
22-04-2022 |
21-04-2022 |
|
683 |
MEC30321 |
TESTING AND CERTIFICATION OF LIFTING TOOLS AND TACKLES |
18-04-2022 |
16-04-2022 |
|
684 |
MAT/PUR/10852/22(GEM/2022/B/2095776) |
SUPPLY OF SULPHURIC ACID (IS-266 (1993)) |
21-04-2022 |
20-04-2022 |
|
685 |
MAT/PUR/10853/22 |
Supply of MS BARRELS, 200/210 Litre capacity, 18
gauge thickness and conforming to IS-1783 (Part-I) 2014 Grade A
or Latest |
18-04-2022 |
16-04-2022 |
|
686 |
MAT/PUR/10851/22 |
HM-HDPE CARBOUYS |
07-05-2022 |
06-05-2022 |
|
687 |
HOC/FIN/COSTAUDIT/2022-23 |
Appointment of Cost Auditors for the Financial Year 2022-23 (Revised) |
04-05-2022 |
04-05-2022 |
|
688 |
MEC30319 |
RECONDITIONING OF MECHANICAL SEAL |
12-05-2022 |
11-05-2022 |
|
689 |
MAT/PUR/32892/2022 |
HIGH SPEED ALL GEARED PRECISION LATHE MACHINE WITH ACCESSORIES. |
17-05-2022 |
16-05-2022 |
|
690 |
MAT/PUR/32881-B/22 |
PROCUREMENT OF RERUN COLUMN BOTTOM PUMP (P-5504 A/B) &
OVERHEAD PUMP (P-5505 A/B) PUMP ASSEMBLY |
17-05-2022 |
16-05-2022 |
|
691 |
MAT/PUR/22111/22 - 2022_HOCL_687999_1 |
PROCUREMENT OF CT & PT |
31-05-2022 |
30-05-2022 |
|
692 |
MEC30323 (GEM/2022/B/2173042) |
MAINTENANCE OF HEAT EXCHANGER - E 4507 A/B & EJECTOR
COOLERS |
01-06-2022 |
31-05-2022 |
|
693 |
PAD/2022/004 |
Renewal Group Personal Accident Policy for Regular Employees for the Year 2022-23 |
03-06-2022 |
02-06-2022 |
|
694 |
MAT/PUR/32911/22 |
GI MATERIAL FOR COOLING TOWER HANDRAILS |
16-06-2022 |
15-06-2022 |
|
695 |
HOC/PAD/ADMIN 2022-2023/01 |
Providing Security Guard at Corporate/Marketing Office at CBD Belapur, Navi Mumbai.
|
15-06-2022 |
15-06-2022 |
|
696 |
MAT/PUR/32919/22 |
ALUMINIUM SHEET IN COIL FORM |
28-06-2022 |
27-06-2022 |
|
697 |
MAT/PUR/10855/22(GEM/2022/B/2240275) |
MS BARRELS 6000 NOS |
20-06-2022 |
20-06-2022 |
|
698 |
MEC30327 |
Cleaning of Tube Bundles by Hydroblasting - Annual Rate Contract |
27-06-2022 |
25-06-2022 |
|
699 |
MAT/PUR/10856/22 |
Supply of Caustic Soda Lye Rayon Grade conforming to
IS-252-2013 (Latest) with consistent concentration of
31% to 49 % NaOH basis |
29-06-2022 |
28-06-2022 |
|
700 |
MAT/PUR/32887-B/22 |
Complete Pump Assembly of Clarified Water Pump |
02-07-2022 |
01-07-2022 |
|
701 |
MEC30326 |
WRAPPING COATING AND COLD INSULATION WORK |
02-07-2022 |
01-07-2022 |
|
702 |
MAT/PUR/22111 B/22 |
CT AND PT |
05-07-2022 |
04-07-2022 |
|
703 |
MAT/PUR/32828-B/22 |
MULTI STAGE JOCKEY PUMP FOR FIRE WATER SYSTEM |
07-07-2022 |
06-07-2022 |
|
704 |
CIV10141/70000150 |
ANNUAL RATE CONTRACT FOR REPLACING DAMAGED AC SHEETS OF BOILER HOUSE 2022-23 |
22-06-2022 |
22-06-2022 |
|
705 |
GEM/2022/B/2275449 |
Barrels-Steel Barrels Drums-IS 1783 (Q3)
|
11-07-2022 |
11-07-2022 |
|
706 |
MAT/PUR/50347/22 |
3000 KG OF 2 ETHYL ANTHRA QUINONE (2EAQ) |
08-07-2022 |
07-07-2022 |
|
707 |
MAT/PUR/41933/22-(GEM/2022/B/2290777) |
5 NOS OF DESKTOP COMPUTERS |
04-07-2022 |
04-07-2022 |
|
708 |
MAT/PUR/32927/22 |
GASKET SHEETS |
16-07-2022 |
15-07-2022 |
|
709 |
MAT/PUR/32911-B/22 |
GI MATERIAL FOR COOLING TOWER HANDRILS |
01-07-2022 |
30-06-2022 |
|
710 |
MAT/PUR/50346/22 |
SUPPLY OF SOLVESSO 150 |
12-07-2022 |
11-07-2022 |
|
711 |
MAT/PUR/41935/22(GEM/2022/B/2297533) |
35 NOS. OF FIRE HOSE |
08-07-2022 |
08-07-2022 |
|
712 |
CIV10142 |
MISCELLANEOUS CIVIL MAINTENANCE WORK IN HOC TOWNSHIP 2022-2023 |
20-07-2022 |
19-07-2022 |
|
713 |
MEC30328 |
REPAIR OF STRUCTURAL PLATFORM- DIPB PROJECT |
22-07-2022 |
21-07-2022 |
|
714 |
MAT/PUR/10857/22 |
TRANSPORTATION OF BENZENE FROM VARIOUS
SOURCES AS BELOW TO HOCL AMBALAMUGAL
1. BPCL MAHUL REFINARY, MUMBAI
2. IOCL, PANIPAT, HARYANA
3. MRPL, MANGALORE |
21-07-2022 |
20-07-2022 |
|
715 |
MAT/PUR/32929 |
FILTER CANDLES |
22-07-2022 |
21-07-2022 |
|
716 |
MEC30326 |
WRAPPING COATING AND COLD INSULATION WORK - REFLOAT |
19-07-2022 |
18-07-2022 |
|
717 |
MAT/PUR/32933/22 |
CS & SS Valves |
02-08-2022 |
01-08-2022 |
|
718 |
MEC30330 |
MAINTENANCE OF HEAT EXCHANGERS E4517 & E5003 |
15-07-2022 |
14-07-2022 |
|
719 |
MAT/PUR/10858/22-GEM/2022/B/2346141 |
SUPPLY OF SULPHURIC ACID |
29-07-2022 |
29-07-2022 |
|
720 |
MEC30329 |
ERECTION AND REMOVAL OF SCAFFOLDING |
04-08-2022 |
03-08-2022 |
|
721 |
MAT/PUR/50346/B/2022 |
SUPPLY OF SOLVESSO 150 |
27-07-2022 |
26-07-2022 |
|
722 |
MEC30331 |
MAINTENANCE OF HEAT EXCHANGERS & COLUMNS IN PHENOL PLANT |
05-08-2022 |
04-08-2022 |
|
723 |
MRKT/FPS/02/22-24 |
Exclusive Distributor for marketing and sale of Hydrogen Peroxide 6% |
23-08-2022 |
22-08-2022 |
|
724 |
70000154/ELE/22 |
High Mast Trailing cable replacement works |
10-08-2022 |
10-08-2022 |
|
725 |
MAT/PUR/32942/2022 |
CHECK VALVE WAFER TYPE |
12-08-2022 |
11-08-2022 |
|
726 |
MAT/PUR/32941/22 |
MECHANICAL SEAL SPARES FOR P5504 A&B AND P5505 A&B |
17-08-2022 |
16-08-2022 |
|
727 |
MAT/PUR/32937/22 |
MECHANICAL SEAL SPARES FOR P4501/P4505 AND VACCUM PUMP 28K001 |
17-08-2022 |
16-08-2022 |
|
728 |
70000155/MSS/337/2022 |
AMC PRINTER 2022 |
10-08-2022 |
10-08-2022 |
|
729 |
HOCL/MKTG/SALE/O2/22 dt.27.07.2022 |
TENDER FOR SALE OF OFFSPEC CUMOX OIL ON EX-FACTORY BASIS |
10-08-2022 |
10-08-2022 |
|
730 |
PAD/2022/005 |
HOUSE KEEPING AND WASTE DISPOSAL WORK AT HOC
TOWNSHIP FOR THE YEAR 2022-23.
|
23-08-2022 |
23-08-2022 |
|
731 |
MAT/PUR/10855 C/22 |
MS BARREL 6000 NOS |
16-08-2022 |
16-08-2022 |
|
732 |
PAD/2022/006 |
NAMED
GPA POLICY FOR TEMPORARY EMPLOYEES AND UNNAMED GPA POLICY FOR APPRENTICES. |
30-08-2022 |
29-08-2022 |
|
733 |
PAD/2022/008 |
HOUSE KEEPING AND WASTE DISPOSAL WORK AT FACTORY. |
29-09-2022 |
28-09-2022 |
|
734 |
PAD/2022/007 |
CONTRACT FOR ENGAGING UNSKILLED LABOURERS FOR CASUAL JOBS OF MISCELLANEOUS NATURE. |
10-09-2022 |
09-09-2022 |
|
735 |
MAT/PUR/50348/22-GEM/2022/B/2498295 |
SPA (SOLID PHOSPHORIC ACID) CATALYST
|
11-10-2022 |
10-10-2022 |
|
736 |
MAT/PUR/10859/22 |
Transportation of LSHS/ FURNACE OIL-180 FROM BPCL/IOCL/HPCL, WILLINGDON
ISLAND/ERNKULAM/IRIMPANAM TO HOCL, AMBALAMUGAL, KOCHI, KERALA, for a period of 1
year |
22-09-2022 |
21-09-2022 |
|
737 |
PAD/2022/009 |
CONTRACT FOR ENGAGING UNSKILLED LABOURERS FOR
CASUAL JOBS OF MISCELLANEOUS NATURE.
|
07-10-2022 |
06-10-2022 |
|
738 |
MAT/PUR/10861/22 |
Supply of SULPHURIC ACID, as per IS-266(1993), Purity (%w/w) minimum: 98% |
26-09-2022 |
24-09-2022 |
|
739 |
MAT/PUR/50349 /22 |
Supply of 2 Methyl Cyclo Hexyl Acetate ( 2MCA)
|
07-10-2022 |
06-10-2022 |
|
740 |
MAT/PUR/10862/22 |
HIRING OF TEMPO |
07-10-2022 |
06-10-2022 |
|
741 |
HOC/MSS/607/2022-2023 (2022_HOCL_712578/GEM/2022/B/2544461) |
AMC FOR LAN FOR THE PERIOD 2022-2023.
|
07-10-2022 |
06-10-2022 |
|
742 |
PAD/2022/011. |
कैंटीन अनुबंध 2022-23
CANTEEN CONTRACT-2022-23
|
11-10-2022 |
10-10-2022 |
|
743 |
MAT/PUR/32962/22(GEM/2022/B/2548755) |
Intercooler Tube bundle HP for Elliot Air Compressor K 2501 C
Part No : 252521-4
Type : PAP Plus Compressor
Model : 220DA3 (3stage)
Sl.No : C911624B-1 |
27-09-2022 |
27-09-2022 |
|
744 |
MAT/PUR/32942/22 (GEM/2022/B/2546573) |
CHECK VALVE WAFER TYPE |
27-09-2022 |
27-09-2022 |
|
745 |
MEC30334 |
INSPECTION OF PRESSURE VESSELS AND PSVs UNDER FACTORIES RULE - 74 |
14-10-2022 |
13-10-2022 |
|
746 |
MAT/PUR/50348/22-GEM/2022/B/2498295 |
SPA (SOLID PHOSPHORIC ACID) CATALYST |
11-10-2022 |
10-10-2022 |
|
747 |
MAT/PUR/32969/22(GEM/2022/B/2572280) |
INSULATION MATERIALS |
04-10-2022 |
04-10-2022 |
|
748 |
MEC30335 |
SKILLED LABOUR SUPPLY |
19-10-2022 |
18-10-2022 |
|
749 |
MAT/PUR/41953/22 (GEM/2022/B/2569609) |
90% MONO AMMONIUM PHOSPHATE DRY CHEMICALS |
05-10-2022 |
05-10-2022 |
|
750 |
MAT/PUR/32963/22(GEM/2022/B/2587084) |
CS SEAMLESS PIPES |
10-10-2022 |
10-10-2022 |
|
751 |
MAT/PUR/32967/22 (GEM/2022/B/2583517) |
Procurement of Servo Gem and Lube Oil |
10-10-2022 |
10-10-2022 |
|
752 |
MAT/PUR/50349/22 |
Supply of 2 Methyl Cyclo Hexyl Acetate ( 2MCA) |
07-10-2022 |
06-10-2022 |
|
753 |
MAT/PUR/50349/22 |
Supply of 2 Methyl Cyclo Hexyl Acetate ( 2MCA) |
07-10-2022 |
06-10-2022 |
|
754 |
MAT/PUR/10862/22 |
HIRING OF TEMPO |
07-10-2022 |
06-10-2022 |
|
755 |
MAT/PUR/41958/22 (GEM/2022/B/2599868) |
SAFETY SHOES |
12-10-2022 |
12-10-2022 |
|
756 |
MAT/PUR/32952-B/22(2022_HOCL_715955_1) |
Copper Tube & Brass Tube Fittings |
18-10-2022 |
17-10-2022 |
|
757 |
PAD/2022/012 |
GRASS CUTTING WORK IN PLANT AREAS |
28-10-2022 |
27-10-2022 |
|
758 |
MAT/PUR/22169/22 (GEM/2022/B/2609666) |
SUPPLY OF 45KW VFD, INSTALLATION AND COMMISSIONING OF 45 KW VFD |
17-10-2022 |
17-10-2022 |
|
759 |
MAT/PUR/22170/22 |
350W LED Flood Light Fixtures for High Mast Lighting |
17-10-2022 |
17-10-2022 |
|
760 |
MAT/PUR/32929-B/22 |
FILTER CANDLES |
22-10-2022 |
21-10-2022 |
|
761 |
MAT/PUR/10864/22(GEM/2022/B/2665538 ) |
MS BARRELS OF 6000 NOS |
04-11-2022 |
04-11-2022 |
|
762 |
MEC30336 |
DRILLING HOLES 20 MM DIA ON REACTOR FILTER ELEMENT OF V 2007 |
11-11-2022 |
10-11-2022 |
|
763 |
CIV10149 |
MODIFICATION AND RESURFACING OF ROADS AT HOC TOWNSHIP |
16-11-2022 |
15-11-2022 |
|
764 |
CIV10149 |
MODIFICATION AND RESURFACING OF ROADS AT HOC TOWNSHIP |
16-11-2022 |
15-11-2022 |
|
765 |
GEM/2022/B/2689156 |
ENERGY AUDIT SERVICES |
21-11-2022 |
21-11-2022 |
|
766 |
MAT/PUR/32977/22 (GEM/2022/B/2689338) |
P3503 H2SO4 CIRCULATION PUMP ASSEMBLY |
11-11-2022 |
11-11-2022 |
|
767 |
CIV10150/2022 |
RECONSTRUCTION OF COMPOUND WALL AT EAST SIDE OF HOLDING POND |
23-11-2022 |
22-11-2022 |
|
768 |
MAT/PUR/41973/22 (GEM/2022/B/2700890) |
PERSONAL COMPUTERS |
14-11-2022 |
14-11-2022 |
|
769 |
CIV10146/2022 |
REPAIRS TO RCC STRUCTURES IN PLANT AREA 2022 |
25-11-2022 |
24-11-2022 |
|
770 |
CIV10146/2022 |
REPAIRS TO RCC STRUCTURES IN PLANT AREA 2022 |
25-11-2022 |
24-11-2022 |
|
771 |
PAD/2022/013 |
GRASS CUTTING WORK IN NON PLANT AREAS |
24-11-2022 |
23-11-2022 |
|
772 |
MAT/PUR/10865/22 |
NITRIC ACID (58-60% CONCENTRATION) |
18-11-2022 |
17-11-2022 |
|
773 |
CIV10147 |
PAINTING OF ADMINISTRATIVE BUILDING OUTSIDE PORTION |
29-11-2022 |
28-11-2022 |
|
774 |
MAT/PUR/32989/22 |
VIRGIN COCONUT SHELL BASED STEAM ACIVATED CARBON IN GRANULAR FORM |
18-11-2022 |
18-11-2022 |
|
775 |
MAT/PUR/22170/B/22 |
350W LED FLOOD LIGHT FIXTURES FOR HIGH MAST LIGHTING |
21-11-2022 |
21-11-2022 |
|
776 |
MEC30337 |
ANNUAL MAINTENANCE CONTRACT FOR ELLIOTT AIR COMPRESSORS |
03-12-2022 |
02-12-2022 |
|
777 |
MAT/PUR/41953 B/22 |
90 PERCENTAGE MONO AMMONIUM PHOSPHATE DRY CHEMICAL |
24-11-2022 |
24-11-2022 |
|
778 |
MEC30340(GEM/2022/B/2754717) |
TESTING AND CERTIFICATION OF SAFETY VALVES UNDER SMPV(U)RULES |
29-11-2022 |
28-11-2022 |
|
779 |
MAT/PUR/50350/22 |
SUPPLY OF 2 METHYL CYCLO HEXYLE ACETATE (2MCA) |
06-12-2022 |
05-12-2022 |
|
780 |
MAT/PUR/41977/22 |
PROCUREMENT OF BITUMEN VG 30 PACKED IN 193 KG |
03-12-2022 |
03-12-2022 |
|
781 |
HR/2022/015 |
Renewal of Group Mediclaim Insurance Policy for Retired/VRS opted Employees &
their Spouses and Spouses of deceased employees for the Year 2023-24 |
17-12-2022 |
16-12-2022 |
|
782 |
HR/2022/015 |
Renewal of Group Mediclaim Insurance Policy for Retired/VRS opted Employees &
their Spouses and Spouses of deceased employees for the Year 2023-24 |
17-12-2022 |
16-12-2022 |
|
783 |
MAT/PUR/10866/22 |
SUPPLY OF MONOSODIUM PHOSPHATE MONOHYDRATE |
14-12-2022 |
13-12-2022 |
|
784 |
MAT/PUR/10867/22 |
HM HDPE CARBOUYS 13000 NOS |
16-12-2022 |
15-12-2022 |
|
785 |
HR/2022/014 |
CONTRACT FOR SECURITY ARRANGEMENTS AT HOC TOWNSHIP FOR THE YEAR 2023-24 |
23-12-2022 |
22-12-2022 |
|
786 |
MEC30338 |
INSULATION WRAPPING AND COATING WORKS |
28-12-2022 |
27-12-2022 |
|
787 |
MEC30341 |
ULTRASONIC THICKNESS SURVEY OF PIPING AND EQUIPMENT |
27-12-2022 |
26-12-2022 |
|
788 |
MAT/PUR/10868/22 |
SULPHURIC ACID |
17-12-2022 |
16-12-2022 |
|
789 |
CIV10148/2022 |
MODIFICATION REPAIR AND RESURFACING OF ROADS IN PLANT AND NON PLANT AREAS FACTORY |
27-12-2022 |
26-12-2022 |
|
790 |
MAT/PUR/33003/22( GEM/2022/B/2828463 ) |
Procurement of CS AND SS VALVES |
19-12-2022 |
19-12-2022 |
|
791 |
MAT/PUR/33003/22(GEM/2022/B/2828463 ) |
Procurement of CS AND SS VALVES |
19-12-2022 |
19-12-2022 |
|
792 |
MAT/PUR/33002/22 (GEM/2022/B/2828040) |
Procurement of CS AND SS PIPES |
19-12-2022 |
19-12-2022 |
|
793 |
MAT/PUR/22188/22 |
FLAME PROOF LED WELL GLASS LIGHT FIXTURE 45 W |
23-12-2022 |
23-12-2022 |
|
794 |
MAT/PUR/22188/22(GEM/2022/B/2850299) |
FLAME PROOF LED WELL GLASS LIGHT FIXTURE 45W |
23-12-2022 |
23-12-2022 |
|
795 |
700000178/ DT.27.12.2022 |
CLEANING OF MEA MAN HOLES AND PIPELINES 2022-2023 |
04-01-2023 |
04-01-2023 |
|
796 |
MEC30345 |
SUPPLY , FABRICATION, TESTING AND TRANSPORTATION OF HOT WATER TANK - 28 D 004 IN H2O2 CONCENTRATION UNIT |
25-01-2023 |
24-01-2023 |
|
797 |
MEC30344 |
Painting of Piping & Structural and Equipment in Fractionation,
Hydrogenation, CPP (Licensed Area) & Pipelines in Tankage Area |
02-02-2023 |
01-02-2023 |
|
798 |
MEC30343 |
SUPPLY, FABRICATION, TESTING AND TRANSPORTATION OF SHELL AND DISH END OF DEPROPANISER OVERHEAD CONDENSER (E-2004) |
25-01-2023 |
24-01-2023 |
|
799 |
MAT/PUR/10872/22 |
Supply of Caustic Soda Lye Rayon Grade conforming to
IS-252-2013 (Latest) with consistent concentration of
31% to 49 % NaOH basis |
19-01-2023 |
18-01-2023 |
|
800 |
MAT/PUR/50350 B/22 (GEM/2023/B/2966348) |
SUPPLY OF 2 METHYL CYCLO HEXYL ACETATE (2MCA) |
20-01-2023 |
19-01-2023 |
|
801 |
MAT/PUR/10874/23 (GEM/2023/B/2969169) |
MS BARRELS (7500 NOS) |
20-01-2023 |
20-01-2023 |
|
802 |
UTY30154 |
ANNUAL CLEANING AND INSPECTION OF WASTE HEAT BOILERS K616 & K 617 |
13-02-2023 |
10-02-2023 |
|
803 |
MEC30348 |
AMC FOR COLES CRANE |
02-02-2023 |
01-02-2023 |
|
804 |
MEC30346 |
SERVICING AND RECONDITIONING OF FILTER CANDLES ( SIZE : 2μM x 64 x
762 mm LENGTH) |
02-02-2023 |
01-02-2023 |
|
805 |
CIV10157/2023 |
MODIFICATION WORKS IN GUEST HOUSE AND KITCHEN AT HOC TOWNSHIP |
01-02-2023 |
01-02-2023 |
|
806 |
HOC/ELE/H2O2-UTY/590 |
MISCELLANEOUS ELECTRICAL WORKS 2023-2025 |
21-02-2023 |
20-02-2023 |
|
807 |
CIV10153/2023 |
ADDITIONAL MISCELLANEOUS CIVIL MAINTENANCE WORKS IN PLANT AND NON PLANT AREAS 2023 |
16-02-2023 |
15-02-2023 |
|
808 |
CIV10154/2023 |
HIRING OF MECHANICAL EXCAVATOR, TIPPER AND PUMP SET 2022-2023 |
22-02-2023 |
21-02-2023 |
|
809 |
MAT/PUR/10875/23 |
SUPPLY OF CITRIC ACID FOOD GRADE 99.5%- 100.5% |
21-02-2023 |
20-02-2023 |
|
810 |
MAT/PUR/50352/23 |
SUPPLY OF SOLVESSO 150 |
18-02-2023 |
17-02-2023 |
|
811 |
MAT/PUR/50351/23 |
2 ETHYL ANTHRA QUINON (2 EAQ) |
24-02-2023 |
23-02-2023 |
|
812 |
MAT/PUR/33029/23 |
TEFLON FILTER CLOTH FOR REACTOR FILTER |
27-02-2023 |
27-02-2023 |
|
813 |
GEM/2023/B/3161040 |
DIGITAL DENSITY METER (Q3) |
03-03-2023 |
03-03-2023 |
|
814 |
GEM/2023/B/3161040 |
DIGITAL DENSITY METER |
03-03-2023 |
03-03-2023 |
|
815 |
GEM/2023/B/3139179 |
Portable Fire Extinguishers as per IS 15683 (2018) Version 2
(Q2) |
27-02-2023 |
27-02-2023 |
|
816 |
MEC30350 |
HIRING OF MOBILE CRANES AND MANLIFT MACHINES |
15-03-2023 |
14-03-2023 |
|
817 |
GEM/2023/B/3139094 |
Fire Extinguisher Cabinet |
27-02-2023 |
27-02-2023 |
|
818 |
MEC30349 |
REPAIR OF STRUCTURAL PLATFORM |
16-03-2023 |
15-03-2023 |
|
819 |
MEC30349 |
REPAIR OF STRUCTURAL PLATFORM |
16-03-2023 |
15-03-2023 |
|
820 |
gg |
gg |
23-02-2023 |
23-02-2023 |
|
821 |
MAT/PUR/33002-B/23 |
CS AND SS PIPES |
06-03-2023 |
06-03-2023 |
|
822 |
MAT/PUR/42003/23 |
MULTIPURPOSE HAND CONTROLLED NOZZLE |
10-03-2023 |
10-03-2023 |
|
823 |
MAT/PUR/42003/23 |
MULTIPURPOSE HAND CONTROLLED NOZZLE |
10-03-2023 |
10-03-2023 |
|
824 |
MAT/PUR/33032/23 |
VIBRATION ANALYZER |
13-03-2023 |
13-03-2023 |
|
825 |
MAT/PUR/33032/23 |
VIBRATION ANALYZER |
13-03-2023 |
13-03-2023 |
|
826 |
UTY30155 |
RLA STUDY OF MAIN BOLIERS K 479 & K 480 |
22-03-2023 |
21-03-2023 |
|
827 |
GEM/2023/B/3223468 |
SPARES FOR INSTRUMENT AIR COMPRESSOR-||| |
18-03-2023 |
18-03-2023 |
|
828 |
UTY30156 |
ANNUAL CLEANING AND INSPECTION OF BOILERS K479, K480 & K607 |
30-03-2023 |
30-03-2023 |
|
829 |
MEC30352 |
MAINTENANCE OF HEAT EXCHANGERS |
17-03-2023 |
16-03-2023 |
|
830 |
MAT/PUR/10879/23 |
SULPHURIC ACID-120MT |
24-03-2023 |
24-03-2023 |
|
831 |
MAT/PUR/50353/23 |
2 Methyl Cyclo Hexyl Acetate |
29-03-2023 |
28-03-2023 |
|
832 |
HR/2023/003 |
a) HIRING OF AN AC AMBULANCE FOR HOCL KOCHI UNIT.
b) Hiring OF A 5 SEATER AC DIESEL CAR FOR HOCL KOCHI UNIT |
11-04-2023 |
10-04-2023 |
|
833 |
GEM/2023/B/3272666 |
CS SEAMLESS PIPES |
30-03-2023 |
30-03-2023 |
|
834 |
GEM/2023/B/3284863 |
VIRGIN COCONUT SHELL BASED STEAM ACTIVATED CARBON IN GRANULAR FORM |
01-04-2023 |
01-04-2023 |
|
835 |
MEC30355 |
HIRING OF MOBILE CRANES |
06-04-2023 |
05-04-2023 |
|
836 |
GEM/2023/B/3292339 |
MECHANICAL SEAL SPARES |
04-04-2023 |
04-04-2023 |
|
837 |
GEM/2023/B/3291897 |
CS & SS SEAMLESS PIPE & PIPE FITTINGS |
04-04-2023 |
04-04-2023 |
|
838 |
GEM/2023/B/3295847 |
INSTRUMENTATION FITTINGS |
05-04-2023 |
05-04-2023 |
|
839 |
GEM/2023/B/3304524 |
SPARE FOR PHENOL LOADING ARM |
08-04-2023 |
08-04-2023 |
|
840 |
GEM/2023/B/3304794 |
STRUCTURAL ITEMS |
08-04-2023 |
08-04-2023 |
|
841 |
GEM/2023/B/3304731 |
SS WINDING WIRE |
08-04-2023 |
08-04-2023 |
|
842 |
MAT/PUR/42010/23 |
PRINTERS |
10-04-2023 |
10-04-2023 |
|
843 |
GEM/2023/B/3308439 |
MECHANICAL SEAL SPARES FOR DURAMETALLIC SEALS |
10-04-2023 |
10-04-2023 |
|
844 |
MEC30351 |
PAINTING OF PIPING & STRUCTURAL AND EQUIPMENT IN H2O2 PLANT INCLUDING CONCENTRATION UNIT |
20-04-2023 |
19-04-2023 |
|
845 |
GEM/2023/B/3324143 |
COOLING TOWER FAN BLADES WITH BLADE CLAMPS AND HUB ASSEMBLY |
15-04-2023 |
15-04-2023 |
|
846 |
GEM/2023/B/3327335 |
STUD WITH TWO NUTS |
17-04-2023 |
17-04-2023 |
|